| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 23 Oct 2026 | Package 2- Work started and in progress- 10 % completed. package 1- Work completed and final bill submitted . Package 3- Site Handed over and pipe supplied. Package 4- Sakthikulangra& Thrikkadavoor area- AC plugging and alteration works in progressing- 70% completed. | Kollam WS Sn 2 - AE | |
| 15 Oct 2026 | Package 2- Work started and in progress- 10 % completed. package 1- Work completed and final bill submitted . Package 3- Site Handed over and pipe supplied. Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work and alteration works in progressing- 65% completed. | Kollam WS Sn 2 - AE | |
| 06 Oct 2026 | Package 1- Work started and in progress- 1 % completed. package 2- Work completed and final bill submitted Package 3- Site Handed over. Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work and alteration works in progressing- 60% completed. | Kollam WS Sn 2 - AE | |
| 01 Oct 2026 | Package 1- Work started and in progress- 1 % completed. package 2- Work completed and final bill submitted Package 3- Site Handed over. Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work in progressing- 60% completed. | Kollam WS Sn 2 - AE | |
| 23 Sep 2026 | Package 1- Work started and in progress- 1 % completed. package 2- Work completed and final bill submitted Package 3- Agreement execution under process. Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work in progressing- 60% completed. | Kollam WS Sn 2 - AE | |
| 19 Sep 2026 | Package 1- Work started and in progress- 1 % completed. package 2- Work completed and final bill submitted Package 3- Agreement execution under process. Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work in progressing- 40% completed. | Kollam WS Sn 2 - AE | |
| 14 Sep 2026 | Package 1- Work started and in progress- 1 % completed. package 2- Work completed and final bill submitted Package 3- Agreement execution under process. Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work in progressing- 35% completed. | Kollam WS Sn 2 - AE | |
| 11 Sep 2026 | Package 1- Work started and in progress- 1 % completed. package 2- Work completed and final bill submitted Package 3- Agreement execution under process. Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work in progressing- 20% completed. | Kollam WS Sn 2 - AE | |
| 08 Sep 2026 | Package 1- Work started and in progress- 1 % completed. package 2- Work completed and final bill submitted Package 3- Agreement execution under process. Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work in progressing- 5% completed. | Kollam WS Sn 2 - AE | |
| 01 Sep 2026 | Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work started and progressing. | Kollam WS Sn 2 - AE |