Overall Project Status

Status Date Overall Project Status Project Officer Contact
23 Oct 2026 Package 2- Work started and in progress- 10 % completed. package 1- Work completed and final bill submitted . Package 3- Site Handed over and pipe supplied. Package 4- Sakthikulangra& Thrikkadavoor area- AC plugging and alteration works in progressing- 70% completed. Kollam WS Sn 2 - AE
15 Oct 2026 Package 2- Work started and in progress- 10 % completed. package 1- Work completed and final bill submitted . Package 3- Site Handed over and pipe supplied. Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work and alteration works in progressing- 65% completed. Kollam WS Sn 2 - AE
06 Oct 2026 Package 1- Work started and in progress- 1 % completed. package 2- Work completed and final bill submitted Package 3- Site Handed over. Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work and alteration works in progressing- 60% completed. Kollam WS Sn 2 - AE
01 Oct 2026 Package 1- Work started and in progress- 1 % completed. package 2- Work completed and final bill submitted Package 3- Site Handed over. Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work in progressing- 60% completed. Kollam WS Sn 2 - AE
23 Sep 2026 Package 1- Work started and in progress- 1 % completed. package 2- Work completed and final bill submitted Package 3- Agreement execution under process. Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work in progressing- 60% completed. Kollam WS Sn 2 - AE
19 Sep 2026 Package 1- Work started and in progress- 1 % completed. package 2- Work completed and final bill submitted Package 3- Agreement execution under process. Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work in progressing- 40% completed. Kollam WS Sn 2 - AE
14 Sep 2026 Package 1- Work started and in progress- 1 % completed. package 2- Work completed and final bill submitted Package 3- Agreement execution under process. Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work in progressing- 35% completed. Kollam WS Sn 2 - AE
11 Sep 2026 Package 1- Work started and in progress- 1 % completed. package 2- Work completed and final bill submitted Package 3- Agreement execution under process. Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work in progressing- 20% completed. Kollam WS Sn 2 - AE
08 Sep 2026 Package 1- Work started and in progress- 1 % completed. package 2- Work completed and final bill submitted Package 3- Agreement execution under process. Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work in progressing- 5% completed. Kollam WS Sn 2 - AE
01 Sep 2026 Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work started and progressing. Kollam WS Sn 2 - AE