DEPOSIT-RWSS to NEDUMPANA-Replacement of Existing old damaged PVC Pipes and Providing interconnection works and in Various Wards of Nedumpana Grama Panchayath

Project DEPOSIT-RWSS to NEDUMPANA-Replacement of Existing old damaged PVC Pipes and Providing interconnection works and in Various Wards of Nedumpana Grama Panchayath
Project Code KLMDEPO032517227
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-RWSS to NEDUMPANA-Replacement of Existing old damaged PVC Pipes and Providing interconnection works and in Various Wards of Nedumpana Grama Panchayath
Status Completed
District Kollam
Executing Office Kottiyam PH Sn
AS Amount (Rs) 2790000
AS Number SC2-02/25
TS Amount (Rs)
TS Number
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
No Packages has been added for this project.

Overall Project Status

Status Date Overall Project Status Project Officer Contact
10 Feb 2026 Work completed. Measurement recorded Kottiyam PH Sn AE
04 Feb 2026 Malayavayal Kanjirathinkal Colony Road Pipe Laying Work Completed. Ward-13 SKV Chalakkara road pipe replacement work completed. Measurement recorded Kottiyam PH Sn AE
30 Jan 2026 Malayavayal Kanjirathinkal Colony Road Pipe Laying Work Completed. Ward-13 SKV Chalakkara road pipe replacement work completed. Measurement recorded Kottiyam PH Sn AE
27 Jan 2026 Malayavayal Kanjirathinkal Colony Road Pipe Laying Work Completed. Ward-13 SKV Chalakkara road pipe replacement work completed. Measurement recorded. Kottiyam PH Sn AE
23 Jan 2026 Malayavayal Kanjirathinkal Colony Road Pipe Laying Work Completed. Ward-13 SKV Chalakkara road pipe replacement work completed. Kottiyam PH Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 10/03/2025
Scheduled date of Completion of the Project 09 Jun 2025
Expected date of Completion 09/06/2025

Processing Dates

AS Date 10 Mar 2025

Other details