Overall Project Status

Status Date Overall Project Status Project Officer Contact
10 Feb 2026 Work completed. Measurement recorded Kottiyam PH Sn AE
04 Feb 2026 Malayavayal Kanjirathinkal Colony Road Pipe Laying Work Completed. Ward-13 SKV Chalakkara road pipe replacement work completed. Measurement recorded Kottiyam PH Sn AE
30 Jan 2026 Malayavayal Kanjirathinkal Colony Road Pipe Laying Work Completed. Ward-13 SKV Chalakkara road pipe replacement work completed. Measurement recorded Kottiyam PH Sn AE
27 Jan 2026 Malayavayal Kanjirathinkal Colony Road Pipe Laying Work Completed. Ward-13 SKV Chalakkara road pipe replacement work completed. Measurement recorded. Kottiyam PH Sn AE
23 Jan 2026 Malayavayal Kanjirathinkal Colony Road Pipe Laying Work Completed. Ward-13 SKV Chalakkara road pipe replacement work completed. Kottiyam PH Sn AE
20 Jan 2026 Malayavayal Kanjirathinkal Colony Road Pipe Laying Work Completed. Ward-13 SKV Chalakkara road pipe replacement work in progress. Kottiyam PH Sn AE
16 Jan 2026 Malayavayal Kanjirathinkal Colony Road Pipe Laying Work Completed Kottiyam PH Sn AE
12 Jan 2026 Malayavayal Kanjirathinkal colony road pipe laying work completed Kottiyam PH Sn AE
12 Jan 2026 Ward 8-Malayavayal Kanjirathinkal colony road Work in progress. Kottiyam PH Sn AE
08 Jan 2026 Ward 12-Pallimon Darshanam jn 75mm PVC Pipe 140m laying work &10 No.s Alteration work completed. Ward 12-Pallimon Majistrate jn Sidhartha road 75mm PVC Pipe 220m laying work &7 No.s Alteration work completed. Work in progress. Kottiyam PH Sn AE