JJM VANDAZHY-Jal Jeevan Mission (JJM)-Jal Jeevan Mission Providing FHTCs (6055nos) in Low Level Zone of Vandazhy Grama Panchayath from 24.5LL OHSR at Mangalam Dam WTP-Providing FHTCS

Project JJM VANDAZHY-Jal Jeevan Mission (JJM)-Jal Jeevan Mission Providing FHTCs (6055nos) in Low Level Zone of Vandazhy Grama Panchayath from 24.5LL OHSR at Mangalam Dam WTP-Providing FHTCS
Project Code PKDJJM022214392P1
Type Package
Main Project JJM VANDAZHY-Jal Jeevan Mission (JJM)-Jal Jeevan Mission Providing FHTCs (6055nos) in Low Level Zone of Vandazhy Grama Panchayath from 24.5LL OHSR at Mangalam Dam WTP-Providing FHTCS
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM VANDAZHY-Jal Jeevan Mission (JJM)-Jal Jeevan Mission Providing FHTCs (6055nos) in Low Level Zone of Vandazhy Grama Panchayath from 24.5LL OHSR at Mangalam Dam WTP-Providing FHTCS
Status On-going
District Palakkad
Executing Office Chittur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 96800000
TS Number ORDER No.: WRD/KWA-CEP/EST_TS/307/2022_26_1_1 Dated: 25-11-2022
Technical specification Providing FHTCs (6055nos) in Low Level Zone of Vandazhy Grama Panchayath from 24.5LL OHSR at Mangalam Dam WTP-Providing FHTCS
Contractor Hamza Valiyaparambil (Mob: 9846520965)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 31/03/2023
Scheduled date of Completion as per agreement 30 Sep 2023
Expected date of Completion 31/12/2024

Processing Dates

TS Date 25 Nov 2022
Estimate Approval 25 Nov 2022
NIT Approval 31 Mar 2023
Tender Closing 21 Feb 2023
Technichal Pre-Qualification 13 Feb 2023
Price bid opening 22 Feb 2023

Approval Dates

Workorder Date 31 Mar 2023
NA 21 Mar 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chittur Project Dn - AE 3
Date: 27/06/2024

Work in progress | 60% Completed

TOTAL PIPE LAID 5.460km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe- 2460 m FHTC- 3084 Nos provided/out of 6055.

Chittur Project Dn - AE 3
Date: 20/06/2024

Work in progress | 60% Completed

TOTAL PIPE LAID 5.460km laid/8km pipe 1.) 90mm PVC 6 kg -3.00km laid 2) 80mm GI pipe- 2460 m FHTC- 3084 Nos provided/out of 6055.