JJM - Kasaragod District -Muliyar and Chengala Panchayaths- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 6(Zone 2)-Laying Distribution system and providing FHTCs- from OHSR at Boikkanam..
Project |
JJM - Kasaragod District -Muliyar and Chengala Panchayaths- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 6(Zone 2)-Laying Distribution system and providing FHTCs- from OHSR at Boikkanam.. |
Project Code |
KGDJJM092110792 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-01 |
Description |
Muliyar and Chengala Panchayaths- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 6(Zone 2)-Laying Distribution system and providing FHTCs- from OHSR at Boikkanam. |
Status |
On-going |
District |
Kasaragod |
Executing Office |
Kanhangad Project Division |
AS Amount (Rs) |
1272000000
|
AS Number |
G.O(Rt)No.489/2021/WRD |
TS Amount (Rs) |
366200000 |
TS Number |
TS/2021-2022/2021/41501 |
Total Bill Submitted (Rs) |
154784299 |
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
17 Dec 2022 |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
JJM - Kasaragod District -Muliyar and Chengala Panchayaths- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 6(Zone 2)-Laying Distribution system and providing FHTCs- from OHSR at Boikkanam.. |
Project Division Kannur ( KGD) |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
10 Mar 2025 |
1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted. |
Kanhangad Proj Dn AE - 2 |
|
03 Mar 2025 |
1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted. |
Kanhangad Proj Dn AE - 2 |
|
24 Feb 2025 |
1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted. |
Kanhangad Proj Dn AE - 2 |
|
20 Feb 2025 |
1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted. |
Kanhangad Proj Dn AE - 2 |
|
15 Feb 2025 |
1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted. |
Kanhangad Proj Dn AE - 2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
Date is not specified |
Scheduled date of Completion of the Project |
17 Dec 2022 |
Expected date of Completion |
31/03/2024 |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
14 Dec 2021 |