Project | JJM - Kasaragod District -Muliyar and Chengala Panchayaths- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 6(Zone 2)-Laying Distribution system and providing FHTCs- from OHSR at Boikkanam.. |
---|---|
Project Code | KGDJJM092110792P1 |
Type | Package |
Main Project | JJM - Kasaragod District -Muliyar and Chengala Panchayaths- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 6(Zone 2)-Laying Distribution system and providing FHTCs- from OHSR at Boikkanam.. |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-01 |
Description | Muliyar and Chengala Panchayaths- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 6(Zone 2)-Laying Distribution system and providing FHTCs- from OHSR at Boikkanam.. |
Status | On-going |
District | Kasaragod |
Executing Office | Project Division Kannur ( KGD) |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 366200000 |
TS Number | TS/2021-2022/2021/41501 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | 17 Dec 2022 |
Expected date of Completion | 30/06/2024 |
TS Date | 14 Dec 2021 |
---|
Workorder Date | 18 Mar 2022 |
---|---|
NA | 04 Apr 2022 |
Kanhangad Proj Dn AE - 2 |
Date: 10/03/2025 |
Work in progress | 74% Completed
1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted..
Kanhangad Proj Dn AE - 2 |
Date: 03/03/2025 |
Work in progress | 74% Completed
1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted..