JJM - Kasaragod District -Muliyar and Chengala Panchayaths- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 6(Zone 2)-Laying Distribution system and providing FHTCs- from OHSR at Boikkanam..

Project JJM - Kasaragod District -Muliyar and Chengala Panchayaths- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 6(Zone 2)-Laying Distribution system and providing FHTCs- from OHSR at Boikkanam..
Project Code KGDJJM092110792P1
Type Package
Main Project JJM - Kasaragod District -Muliyar and Chengala Panchayaths- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 6(Zone 2)-Laying Distribution system and providing FHTCs- from OHSR at Boikkanam..
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Muliyar and Chengala Panchayaths- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 6(Zone 2)-Laying Distribution system and providing FHTCs- from OHSR at Boikkanam..
Status On-going
District Kasaragod
Executing Office Project Division Kannur ( KGD)
Agreement Number
Agreement Date
TS Amount (Rs) 366200000
TS Number TS/2021-2022/2021/41501
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement 17 Dec 2022
Expected date of Completion 30/06/2024

Processing Dates

TS Date 14 Dec 2021

Approval Dates

Workorder Date 18 Mar 2022
NA 04 Apr 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kanhangad Proj Dn AE - 2
Date: 10/03/2025

Work in progress | 74% Completed

1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted..

Kanhangad Proj Dn AE - 2
Date: 03/03/2025

Work in progress | 74% Completed

1701 nos of HTC billed ( 423 nos HTC in Muliyar panchayath and 1278 nos HTC in Chengala Panchayath).108.014 kms pipe line work completed out of 109.623 kms supply.up to date (CC 8th & part bill) submitted..