Project | JJM-Kannur District-WSS to Kottiyur,Kelakam and Kanichar Panchayaths-Laying Distribution system from WTP and Providing FHTCs -Zone I |
---|---|
Project Code | KNRJJM09218490P1 |
Type | Package |
Main Project | JJM-Kannur District-WSS to Kottiyur,Kelakam and Kanichar Panchayaths-Laying Distribution system from WTP and Providing FHTCs -Zone I |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-01 |
Description | Laying Distribution line from Ongoing NABARD aided project and providing 4145 FHTC .total distribution line proposed in this project is 78127 m for main line and 11820 m for laying rider line and parellel line for avoiding road crossing. |
Status | On-going |
District | Kannur |
Executing Office | Koothuparamba Project Sn No2 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 221500000 |
TS Number | 16894/2021-2022 |
Technical specification | Laying Distribution line from Ongoing NABARD aided project and providing 4145 FHTC .total distribution line proposed in this project is 78127 m for main line and 11820 m for laying rider line and parellel line for avoiding road crossing. |
Contractor | HUNIFA MEETHAL (Mob: 9746924449) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 25/04/2022 |
---|---|
Scheduled date of Completion as per agreement | 27 Dec 2022 |
Expected date of Completion | 31/12/2022 |
TS Date | 02 Jan 2022 |
---|---|
Estimate Approval | 02 Jan 2022 |
NIT Approval | 31 Jan 2022 |
Tender Closing | 09 Feb 2022 |
Technichal Pre-Qualification | 11 Feb 2022 |
Price bid opening | 11 Feb 2022 |
Workorder Date | 28 Mar 2022 |
---|---|
NA | 18 Apr 2022 |
Koothuparamba Proj AE 2 |
Date: 11/03/2025 |
Work in progress | 96% Completed
103200 m pipe laid and 201 HTC given, 1784 nos of FHTCs given.
Koothuparamba Proj AE 2 |
Date: 04/03/2025 |
Work in progress | 96% Completed
103200 m pipe laid and 256 HTC given, 1728 nos of FHTCs given.