KIIFB special Investment package - WRD010-05-WSS to Tanur Municipality and adjoining 4 panchayaths Package 1 - Construction of 14 m dia Well cum pump house, Protection works and Supplying, laying, Commissioning 800 mm dia K9 RWPM.

Project KIIFB special Investment package - WRD010-05-WSS to Tanur Municipality and adjoining 4 panchayaths Package 1 - Construction of 14 m dia Well cum pump house, Protection works and Supplying, laying, Commissioning 800 mm dia K9 RWPM.
Project Code MLPKIIFB0117518P1
Type Package
Main Project KIIFB special Investment package - WRD010-05-WSS to Tanur Municipality and adjoining 4 panchayaths
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Design ,construction and commissioning of 14 m dia intake well cum pump house, supply,laying,testing and commissioning of 800mm DI k9 RWPM 13817 m supply laying and commissioning of 200mm DI K9 surge 805m labour: material -1:2.497 Package Cost - 322200000/- Overrun by 13 months and 23 days
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 368900000
TS Number KWA/CE/NR/41/2016-17
Technical specification Design ,construction and commissioning of 14 m dia intake well cum pump house, supply,laying,testing and commissioning of 800mm DI k9 RWPM 13817 m supply laying and commissioning of 200mm DI K9 surge 805m
Contractor Tomco Engineering (P) Ltd (Mob: 9249400000)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
01 Nov 2021 Pending Pending Risks From Other Projects The Project production components have been completed. Laying KSEB dedicated feeder line to RWP is arranged as deposit to KSEB. They have started work by 01-10-21 however the work is halted due to non availability of KSEB department supplied items like A-pole, ABC Cable etc. No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 09/04/2018
Scheduled date of Completion as per agreement 31 Mar 2023
Expected date of Completion 30/09/2021

Processing Dates

TS Date 19 Jan 2017
Estimate Approval 19 Jan 2017
NIT Approval 14 Nov 2017
Tender Closing 07 Dec 2017
Technichal Pre-Qualification 04 Jan 2018
Price bid opening 04 Jan 2018

Approval Dates

Workorder Date 09 Apr 2018
NA 25 May 2018

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malappuram Project Dn AE5
Date: 04/05/2024

Work in progress | 98% Completed

Construction of well cum pump house and raw water pumping main laying got completed except trial run and commissioning. Trial run and commissioning not done due to the lack of power connection. We have paid RS. 1,31,747/- and RS. 1,20,74157/- to KSEB for the dedicated power line extension works on 8/1/2021 for WTP and well cum pump house respectively. For WTP, it is ready to connect. As the power connection at well cum pump house is not ready, we withheld the power connection procedure at WTP to avoid unnecessary power charge. Recently on 11/01/2023 the KSEB informed that the powerline extension work in completed. And ready to give power connection. now we start the procedure for obtaining power connection at Pump house and WTP. Which includes Re validation & permission of electrical inspecterate .

Malappuram Project Dn AE5
Date: 03/05/2024

Work in progress | 98% Completed

Construction of well cum pump house and raw water pumping main laying got completed except trial run and commissioning. Trial run and commissioning not done due to the lack of power connection. We have paid RS. 1,31,747/- and RS. 1,20,74157/- to KSEB for the dedicated power line extension works on 8/1/2021 for WTP and well cum pump house respectively. For WTP, it is ready to connect. As the power connection at well cum pump house is not ready, we withheld the power connection procedure at WTP to avoid unnecessary power charge. Recently on 11/01/2023 the KSEB informed that the powerline extension work in completed. And ready to give power connection. now we start the procedure for obtaining power connection at Pump house and WTP. Which includes Re validation & permission of electrical inspecterate .