KIIFB special Investment package - WRD010-05-WSS to Tanur Municipality and adjoining 4 panchayaths Package 1 - Construction of 14 m dia Well cum pump house, Protection works and Supplying, laying, Commissioning 800 mm dia K9 RWPM.
Project |
KIIFB special Investment package - WRD010-05-WSS to Tanur Municipality and adjoining 4 panchayaths Package 1 - Construction of 14 m dia Well cum pump house, Protection works and Supplying, laying, Commissioning 800 mm dia K9 RWPM. |
Project Code |
MLPKIIFB0117518P1 |
Type |
Package |
Main Project |
KIIFB special Investment package - WRD010-05-WSS to Tanur Municipality and adjoining 4 panchayaths
|
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
Design ,construction and commissioning of 14 m dia intake well cum pump house,
supply,laying,testing and commissioning of 800mm DI k9 RWPM 13817 m
supply laying and commissioning of 200mm DI K9 surge 805m
labour: material -1:2.497
Package Cost - 322200000/-
Overrun by 13 months and 23 days
|
Status |
On-going |
District |
Malappuram |
Executing Office |
Malappuram Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
368900000 |
TS Number |
KWA/CE/NR/41/2016-17 |
Technical specification |
Design ,construction and commissioning of 14 m dia intake well cum pump house,
supply,laying,testing and commissioning of 800mm DI k9 RWPM 13817 m
supply laying and commissioning of 200mm DI K9 surge 805m |
Contractor |
Tomco Engineering (P) Ltd (Mob: 9249400000) |
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
01 Nov 2021 |
Pending |
Pending |
Risks From Other Projects |
The Project production components have been completed. Laying KSEB dedicated feeder line to RWP is arranged as deposit to KSEB. They have started work by 01-10-21 however the work is halted due to non availability of KSEB department supplied items like A-pole, ABC Cable etc. |
No comments available. |
Pending |
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
09/04/2018 |
Scheduled date of Completion as per agreement |
31 Mar 2023 |
Expected date of Completion |
30/09/2021 |
Processing Dates
TS Date |
19 Jan 2017 |
Estimate Approval |
19 Jan 2017 |
NIT Approval |
14 Nov 2017 |
Tender Closing |
07 Dec 2017 |
Technichal Pre-Qualification |
04 Jan 2018 |
Price bid opening |
04 Jan 2018 |
Approval Dates
Workorder Date |
09 Apr 2018 |
NA |
25 May 2018 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Malappuram Project Dn AE5 |
Date: 04/05/2024 |
Work in progress | 98% Completed
Construction of well cum pump house and raw water pumping main laying got completed except trial run and commissioning. Trial run and commissioning not done due to the lack of power connection. We have paid RS. 1,31,747/- and RS. 1,20,74157/- to KSEB for the dedicated power line extension works on 8/1/2021 for WTP and well cum pump house respectively. For WTP, it is ready to connect. As the power connection at well cum pump house is not ready, we withheld the power connection procedure at WTP to avoid unnecessary power charge. Recently on 11/01/2023 the KSEB informed that the powerline extension work in completed. And ready to give power connection. now we start the procedure for obtaining power connection at Pump house and WTP. Which includes Re validation & permission of electrical inspecterate
.
Malappuram Project Dn AE5 |
Date: 03/05/2024 |
Work in progress | 98% Completed
Construction of well cum pump house and raw water pumping main laying got completed except trial run and commissioning. Trial run and commissioning not done due to the lack of power connection. We have paid RS. 1,31,747/- and RS. 1,20,74157/- to KSEB for the dedicated power line extension works on 8/1/2021 for WTP and well cum pump house respectively. For WTP, it is ready to connect. As the power connection at well cum pump house is not ready, we withheld the power connection procedure at WTP to avoid unnecessary power charge. Recently on 11/01/2023 the KSEB informed that the powerline extension work in completed. And ready to give power connection. now we start the procedure for obtaining power connection at Pump house and WTP. Which includes Re validation & permission of electrical inspecterate
.