Project | KIIFB Project: Tranche 21: WRD025-08: Development activities of Drinking Water Project at Mudakkal Panchayath - Augmentation and Rehabilitation of RWSS to Mudakkal Panchayat |
---|---|
Project Code | TVMKIIFB032210763P1 |
Type | Package |
Main Project | KIIFB Project: Tranche 21: WRD025-08: Development activities of Drinking Water Project at Mudakkal Panchayath - Augmentation and Rehabilitation of RWSS to Mudakkal Panchayath |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | The project include Installation of RW Pumps in existing well cum pump house at Ayilam, laying of 400mm DI RWPM for appx. 770m, Construction of a 6 MLD WTP at Ayilam, Installation of CW Pumps in WTP, Laying of 400mm DI K9 CWPM for approx. 4212m to proposed 19 LL OHSR at Nedupuram, laying of 100mm DI K9 for apprx. 1735m upto existing OHSR at Aryiankunnu, Construction of 19LL OHSR at Nedumpuram and laying of 90 mm PVC to 160mm PVC and 150mm DI to 500mm DI for Distribution and Transmission purposes. |
Status | On-going |
District | Thiruvananthapuram |
Executing Office | Trivandrum Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | |
TS Number | |
Technical specification |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
29 Jun 2022 | Pending | Pending | Approval/Permissions Related (from other departments excluding road cut permission and land related) | Approval of LA package in PFMS by KIIFB | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 21/03/2022 |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | 31/12/2023 |
Thiruvananthapuram Project AE5 |
Date: 13/02/2024 |
Work has started | 0% Completed
Revised GO for LA received from Revenue (B) Dept. 4 (1) Notification issued. SIA study in progress.
Thiruvananthapuram Project AE5 |
Date: 12/02/2024 |
Work has started | 0% Completed
Revised GO for LA received from Revenue (B) Dept. 4 (1) Notification issued. SIA study in progress.