JJM - 5th SLSSC - Pipe line extension, Construction of sump cum pump house, Filter media changing and providing 2489 FHTCs in Kaviyoor Grama Panchayath.

Project JJM - 5th SLSSC - Pipe line extension, Construction of sump cum pump house, Filter media changing and providing 2489 FHTCs in Kaviyoor Grama Panchayath.
Project Code PTAJJM022212197
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM - 5th SLSSC - Pipe line extension, Construction of sump cum pump house, Filter media changing and providing 2489 FHTCs in Kaviyoor Grama Panchayath.
Status On-going
District Pathanamthitta
Executing Office Thiruvalla PH Dn
AS Amount (Rs) 70760000
AS Number G.O.(Rt) No.134/2022/WRD of 2022-2023
TS Amount (Rs) 61130000
TS Number 2612/2022-2023
Total Bill Submitted (Rs) 6570164
Total Bill Paid (Rs) 4914753
Population Benefitted 9956
Capacity in MLD 0.99
Actual Project Completion Date 29 Jan 2024
Coverage 2489

Packages

No. Project Name Location View
1 JJM - 5th SLSSC - Pipe line extension, Construction of sump cum pump house, Filter media changing and providing 2489 FHTCs in Kaviyoor Grama Panchayath. Thiruvalla Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
29 Jun 2024 10800 m pipe laid. Compound wall work started at Poovakala pump house. 460 connections given. Construction pump house is in progress. Road restoration work started. Thiruvalla PH Sub Dn - AEE
27 Jun 2024 10800 m pipe laid. Compound wall work started at Poovakala pump house. 460 connections given. Construction pump house is in progress. Road restoration work started. Thiruvalla PH Sub Dn - AEE
24 Jun 2024 10800 m pipe laid. Compound wall work started at Poovakala pump house. 460 connections given. Construction pump house is in progress. Road restoration work started. Thiruvalla PH Sub Dn - AEE
21 Jun 2024 10800 m pipe laid. Compound wall work started at Poovakala pump house. 460 connections given. Construction pump house is in progress. Road restoration work started. Thiruvalla PH Sub Dn - AEE
18 Jun 2024 10800 m pipe laid. Compound wall work started at Poovakala pump house. 460 connections given. Construction pump house is in progress. Road restoration work started. Thiruvalla PH Sub Dn - AEE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 29/07/2022
Scheduled date of Completion of the Project 29 Jan 2024
Expected date of Completion 31/10/2024

Processing Dates

AS Date 23 Feb 2022
TS Date 03 May 2022

Other details

Project Officers View