JJM - 5th SLSSC - Pipe line extension, Construction of sump cum pump house, Filter media changing and providing 2489 FHTCs in Kaviyoor Grama Panchayath.

Project JJM - 5th SLSSC - Pipe line extension, Construction of sump cum pump house, Filter media changing and providing 2489 FHTCs in Kaviyoor Grama Panchayath.
Project Code PTAJJM022212197P1
Type Package
Main Project JJM - 5th SLSSC - Pipe line extension, Construction of sump cum pump house, Filter media changing and providing 2489 FHTCs in Kaviyoor Grama Panchayath.
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM - 5th SLSSC - Pipe line extension, Construction of sump cum pump house, Filter media changing and providing 2489 FHTCs in Kaviyoor Grama Panchayath.
Status On-going
District Pathanamthitta
Executing Office Thiruvalla Sn
Agreement Number
Agreement Date
TS Amount (Rs) 61130000
TS Number 2612/2022-2023
Technical specification Pipe line extension, Construction of sump cum pump house, Filter media changing and providing 2489 FHTCs in Kaviyoor Grama Panchayath.
Contractor PRADEEP KUMAR NT (Mob: 9446741700)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 29/07/2022
Scheduled date of Completion as per agreement 29 Jan 2024
Expected date of Completion 29/01/2024

Processing Dates

TS Date 03 May 2022
Estimate Approval 03 May 2022
NIT Approval 03 May 2022
Tender Closing 06 May 2022
Technichal Pre-Qualification 06 May 2022
Price bid opening 06 May 2022

Approval Dates

Workorder Date 15 Jul 2022
NA 29 Jul 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thiruvalla PH Sub Dn - AEE
Date: 29/06/2024

Work in progress | 50% Completed

10800 m pipe laid. Compound wall work started at Poovakala pump house. 460 connections given. Construction pump house is in progress. Road restoration work started..

Thiruvalla PH Sub Dn - AEE
Date: 27/06/2024

Work in progress | 50% Completed

10800 m pipe laid. Compound wall work started at Poovakala pump house. 460 connections given. Construction pump house is in progress. Road restoration work started..