Project | JJM - 5th SLSSC - Pipe line extension, Construction of sump cum pump house, Filter media changing and providing 2489 FHTCs in Kaviyoor Grama Panchayath. |
---|---|
Project Code | PTAJJM022212197P1 |
Type | Package |
Main Project | JJM - 5th SLSSC - Pipe line extension, Construction of sump cum pump house, Filter media changing and providing 2489 FHTCs in Kaviyoor Grama Panchayath. |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM - 5th SLSSC - Pipe line extension, Construction of sump cum pump house, Filter media changing and providing 2489 FHTCs in Kaviyoor Grama Panchayath. |
Status | On-going |
District | Pathanamthitta |
Executing Office | Thiruvalla Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 61130000 |
TS Number | 2612/2022-2023 |
Technical specification | Pipe line extension, Construction of sump cum pump house, Filter media changing and providing 2489 FHTCs in Kaviyoor Grama Panchayath. |
Contractor | PRADEEP KUMAR NT (Mob: 9446741700) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 29/07/2022 |
---|---|
Scheduled date of Completion as per agreement | 29 Jan 2024 |
Expected date of Completion | 29/01/2024 |
TS Date | 03 May 2022 |
---|---|
Estimate Approval | 03 May 2022 |
NIT Approval | 03 May 2022 |
Tender Closing | 06 May 2022 |
Technichal Pre-Qualification | 06 May 2022 |
Price bid opening | 06 May 2022 |
Workorder Date | 15 Jul 2022 |
---|---|
NA | 29 Jul 2022 |
Thiruvalla PH Sub Dn - AEE |
Date: 29/06/2024 |
Work in progress | 50% Completed
10800 m pipe laid. Compound wall work started at Poovakala pump house. 460 connections given. Construction pump house is in progress. Road restoration work started..
Thiruvalla PH Sub Dn - AEE |
Date: 27/06/2024 |
Work in progress | 50% Completed
10800 m pipe laid. Compound wall work started at Poovakala pump house. 460 connections given. Construction pump house is in progress. Road restoration work started..