Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

WRD005-126-UWSS to Piravom and adjoining panchayaths- Replacement of damaged 250 mm AC gravity main from Kakkadu WTP to Pazhoor sump by laying 250 mm DI pipe line 2650 m

Project WRD005-126-UWSS to Piravom and adjoining panchayaths- Replacement of damaged 250 mm AC gravity main from Kakkadu WTP to Pazhoor sump by laying 250 mm DI pipe line 2650 m
Project Code EKMKIIFB0119520P1
Type Package
Main Project WRD005-126-UWSS to Piravom and adjoining panchayaths- Replacement of damaged 250 mm AC gravity main from Kakkadu WTP to Pazhoor sump by laying 250 mm DI pipe line 2650 m
Funding Agency KIIFB
Category KIIFB WATER SUPPLY SCHEME
Type of scheme Water Supply
Scheme KIIFB
Description Laying of 250mm DI K9 pipe from Kakkad WTP to Pazhoor sump
Status On-going
District Ernakulam
Executing Office Piravam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 15200000
TS Number TS/2019-20/2019/10992 dt 30/10/2019
Technical specification The scope of this work is to supply and laying of 250mm DI K9 Pipes to replace the damaged 250mm AC Pipe Gravity Main

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 20/11/2020
Scheduled date of Completion as per agreement 30 Oct 2022
Expected date of Completion 30/10/2022

Processing Dates

TS Date 30 Oct 2019
Estimate Approval 30 Oct 2019
NIT Approval 11 Nov 2019
Tender Closing 21 Nov 2019
Technichal Pre-Qualification 25 Nov 2019
Price bid opening 25 Nov 2019

Approval Dates

Workorder Date 31 Dec 2019
NA 10 Jan 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Piravom Project Dn AE 1
Date: 27/04/2024

Work in progress | 98% Completed

The remaining works in this contract are 1.Road restoration for a length of 120m to BM&BC standered as per KIIFB norms. 2.Providing 200mm Mechanical flow meter at TP yard Kakkad. 3.Construction of flow meter chamber with Manhole cover. For the balance works an estimate is prepared. .

Piravom Project Dn AE 1
Date: 20/04/2024

Work in progress | 98% Completed

The remaining works in this contract are 1.Road restoration for a length of 120m to BM&BC standered as per KIIFB norms. 2.Providing 200mm Mechanical flow meter at TP yard Kakkad. 3.Construction of flow meter chamber with Manhole cover. For the balance works an estimate is prepared..