Project | WRD005-126-UWSS to Piravom and adjoining panchayaths- Replacement of damaged 250 mm AC gravity main from Kakkadu WTP to Pazhoor sump by laying 250 mm DI pipe line 2650 m |
---|---|
Project Code | EKMKIIFB0119520P1 |
Type | Package |
Main Project | WRD005-126-UWSS to Piravom and adjoining panchayaths- Replacement of damaged 250 mm AC gravity main from Kakkadu WTP to Pazhoor sump by laying 250 mm DI pipe line 2650 m |
Funding Agency | KIIFB |
Category | KIIFB WATER SUPPLY SCHEME |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | Laying of 250mm DI K9 pipe from Kakkad WTP to Pazhoor sump |
Status | On-going |
District | Ernakulam |
Executing Office | Piravam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 15200000 |
TS Number | TS/2019-20/2019/10992 dt 30/10/2019 |
Technical specification | The scope of this work is to supply and laying of 250mm DI K9 Pipes to replace the damaged 250mm AC Pipe Gravity Main |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 20/11/2020 |
---|---|
Scheduled date of Completion as per agreement | 30 Oct 2022 |
Expected date of Completion | 30/10/2022 |
TS Date | 30 Oct 2019 |
---|---|
Estimate Approval | 30 Oct 2019 |
NIT Approval | 11 Nov 2019 |
Tender Closing | 21 Nov 2019 |
Technichal Pre-Qualification | 25 Nov 2019 |
Price bid opening | 25 Nov 2019 |
Workorder Date | 31 Dec 2019 |
---|---|
NA | 10 Jan 2020 |
Piravom Project Dn AE 1 |
Date: 27/04/2024 |
Work in progress | 98% Completed
The remaining works in this contract are 1.Road restoration for a length of 120m to BM&BC standered as per KIIFB norms. 2.Providing 200mm Mechanical flow meter at TP yard Kakkad. 3.Construction of flow meter chamber with Manhole cover. For the balance works an estimate is prepared. .
Piravom Project Dn AE 1 |
Date: 20/04/2024 |
Work in progress | 98% Completed
The remaining works in this contract are 1.Road restoration for a length of 120m to BM&BC standered as per KIIFB norms. 2.Providing 200mm Mechanical flow meter at TP yard Kakkad. 3.Construction of flow meter chamber with Manhole cover. For the balance works an estimate is prepared..