| Project | Budget 2017-2018 KIIFB Project- TRAN10 : WRD 025- 13 WSS to Ramanchadi- Aligarh in Malappuram District-Package 3B - balance transmission main up to KWA office compound |
|---|---|
| Project Code | MLPKIIFB1118510P6 |
| Type | Package |
| Main Project | Budget -2017-2018-KIIFB project-TRAN10:WRD 025-13-WSS to Ramanchadi- Aligarh in Malappuram District |
| Funding Agency | KIIFB |
| Category | KIIFB |
| Type of scheme | Water Supply |
| Scheme | KIIFB |
| Description | This package includes Supplying, Laying, Testing and Commissioning 400mm & 250mm DI K9 pipes |
| Status | On-going |
| District | Malappuram |
| Executing Office | Malappuram Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 57170000 |
| TS Number | TS/2021-2022/2021/16865 |
| Technical specification | Supplying, Laying, Testing and Commissioning 400mm & 250mm DI K9 pipes |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | Date is not specified |
|---|---|
| Scheduled date of Completion as per agreement | 31 Aug 2023 |
| Expected date of Completion | 31/08/2023 |
| TS Date | 12 Nov 2021 |
|---|---|
| Estimate Approval | 12 Nov 2021 |
| NIT Approval | 12 Nov 2021 |
| Tender Closing | 16 Jun 2022 |
| Technichal Pre-Qualification | 08 Jul 2022 |
| Price bid opening | 11 Jul 2022 |
| Workorder Date | 22 Aug 2022 |
|---|
| Malappuram Project Dn AE3 |
| Date: 22/04/2026 |
Work in progress | 98% Completed
Work Completed. Final Bill Under Processing .
| Malappuram Project Dn AE3 |
| Date: 10/04/2026 |
Work in progress | 97% Completed
Work Completed. Bill Under Processing .