Project | JJM POOYAPPALLY-PHASE II-BALANCE PIPE LINE WORK AND PROVIDING BALANCE FHTC IN POOYAPPALLY GRAMA PANCHAYATH |
---|---|
Project Code | KLMJJM102315732P1 |
Type | Package |
Main Project | JJM POOYAPPALLY-BALANCE PIPE LINE WORK AND PROVIDING BALANCE FHTC IN POOYAPPALLY GRAMA PANCHAYATH |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM POOYAPPALLY-PHASE II-BALANCE PIPE LINE WORK AND PROVIDING BALANCE FHTC IN POOYAPPALLY GRAMA PANCHAYATH-SUPPLYING AND LAYING OF BALANCE PIPE LINE WORK |
Status | On-going |
District | Kollam |
Executing Office | Kollam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 9822000 |
TS Number | 19276/2023-2024 dtd 18/11/2023 |
Technical specification | 5km Distribution network, 400nos balance FHTC and allied works |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 28/01/2024 |
---|---|
Scheduled date of Completion as per agreement | 17 Jan 2025 |
Expected date of Completion | 17/01/2025 |
TS Date | 18 Nov 2023 |
---|---|
Estimate Approval | 18 Nov 2023 |
NIT Approval | 25 Nov 2023 |
Tender Closing | 04 Dec 2023 |
Technichal Pre-Qualification | 05 Dec 2023 |
Price bid opening | 05 Dec 2023 |
Workorder Date | 04 Jan 2024 |
---|---|
NA | 18 Jan 2024 |
Kollam Project HD |
Date: 01/07/2024 |
Work in progress | 54% Completed
Work temporarily stopped due to heavy rain.
Kollam Project HD |
Date: 26/06/2024 |
Work in progress | 54% Completed
Geotagging in progress.