JJM POOYAPPALLY-BALANCE PIPE LINE WORK AND PROVIDING BALANCE FHTC IN POOYAPPALLY GRAMA PANCHAYATH
Project |
JJM POOYAPPALLY-BALANCE PIPE LINE WORK AND PROVIDING BALANCE FHTC IN POOYAPPALLY GRAMA PANCHAYATH |
Project Code |
KLMJJM102315732 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
BALANCE PIPE LINE WORK AND PROVIDING BALANCE FHTC IN POOYAPPALLY GRAMA PANCHAYATH - SUPPLYING AND LAYING OF BALANCE PIPE LINE WORK |
Status |
On-going |
District |
Kollam |
Executing Office |
Kollam Project Dn |
AS Amount (Rs) |
44230000
|
AS Number |
Go(Rt)No.897/2023/WRD dtd 26/10/2023 |
TS Amount (Rs) |
9822000 |
TS Number |
19276/2023-2024 dtd 18/11/2023 |
Total Bill Submitted (Rs) |
1053431 |
Total Bill Paid (Rs) |
1053431 |
Population Benefitted |
23924 |
Capacity in MLD |
73.00 |
Actual Project Completion Date |
17 Jan 2025 |
Coverage |
5km Distribution network and 400nos FHTC |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM POOYAPPALLY-PHASE II-BALANCE PIPE LINE WORK AND PROVIDING BALANCE FHTC IN POOYAPPALLY GRAMA PANCHAYATH |
Kollam Project Dn |
|
No status have been added to this project
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
28/01/2024 |
Scheduled date of Completion of the Project |
17 Jan 2025 |
Expected date of Completion |
17/01/2025 |
Processing Dates
AS Date |
26 Oct 2023 |
TS Date |
18 Nov 2023 |