| Project | DEPOSIT-Relaying of Damaged existing pipe from 4th Mile towards Chinnar area on PWD Road-2023-24-Pipeline Work |
|---|---|
| Project Code | IDKKIIFB082417057P1 |
| Type | Package |
| Main Project | DEPOSIT-Relaying of Damaged existing pipe from 4th Mile towards Chinnar area on PWD Road-2023-24-Pipeline Work |
| Funding Agency | KIIFB |
| Category | Deposit Work |
| Type of scheme | Water Supply |
| Scheme | KIIFB |
| Description | DEPOSIT-Relaying of Damaged existing pipe from 4th Mile towards Chinnar area on PWD Road-2023-24-Pipeline Work |
| Status | Completed |
| District | Idukki |
| Executing Office | Peerumedu Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 6052000 |
| TS Number | 12861/2024-2025 |
| Technical specification | Pipeline Work |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 22/10/2024 |
|---|---|
| Scheduled date of Completion as per agreement | 21 Jan 2025 |
| Expected date of Completion | 21/01/2025 |
| TS Date | 09 Sep 2024 |
|---|---|
| Estimate Approval | 09 Sep 2024 |
| NIT Approval | 09 Sep 2024 |
| Tender Closing | 18 Sep 2024 |
| Technichal Pre-Qualification | 18 Sep 2024 |
| Price bid opening | 19 Sep 2024 |
| Workorder Date | 21 Oct 2024 |
|---|---|
| NA | 16 Oct 2024 |
| Peerumedu Sn AE |
| Date: 03/07/2025 |
Work has been completed | 100% Completed
Compleated.
| Peerumedu Sn AE |
| Date: 15/01/2025 |
Work in progress | 5% Completed
Work started.