Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

DEPOSIT-Relaying of Damaged existing pipe from 4th Mile towards Chinnar area on PWD Road-2023-24-Pipeline Work

Project DEPOSIT-Relaying of Damaged existing pipe from 4th Mile towards Chinnar area on PWD Road-2023-24-Pipeline Work
Project Code IDKKIIFB082417057
Type Main project
Funding Agency KIIFB
Category Deposit Work
Type of scheme Water Supply
Scheme KIIFB
Description DEPOSIT-Relaying of Damaged existing pipe from 4th Mile towards Chinnar area on PWD Road-2023-24-Pipeline Work
Status Completed
District Idukki
Executing Office Peerumedu Sn
AS Amount (Rs) 6235000
AS Number RBI2302451134952
TS Amount (Rs) 6052000
TS Number 12861/2024-2025
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 250
Capacity in MLD 9.50
Actual Project Completion Date Date is not specified
Coverage from 4th Mile towards Chinnar area
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 DEPOSIT-Relaying of Damaged existing pipe from 4th Mile towards Chinnar area on PWD Road-2023-24-Pipeline Work Peerumedu Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
03 Jul 2025 Compleated Peerumedu Sn AE
15 Jan 2025 Work started Peerumedu Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 22/10/2024
Scheduled date of Completion of the Project 21 Jan 2025
Expected date of Completion 21/01/2025

Processing Dates

AS Date 19 Aug 2024
TS Date 09 Sep 2024

Other details

Project Officers View