- Home
- DEPOSIT-Relaying of Damaged existing pip...
DEPOSIT-Relaying of Damaged existing pipe from 4th Mile towards Chinnar area on PWD Road-2023-24-Pipeline Work
| Project |
DEPOSIT-Relaying of Damaged existing pipe from 4th Mile towards Chinnar area on PWD Road-2023-24-Pipeline Work |
| Project Code |
IDKKIIFB082417057 |
| Type |
Main project |
| Funding Agency |
KIIFB |
| Category |
Deposit Work |
| Type of scheme |
Water Supply |
| Scheme |
KIIFB |
| Description |
DEPOSIT-Relaying of Damaged existing pipe
from 4th Mile towards Chinnar area on PWD
Road-2023-24-Pipeline Work |
| Status |
Completed |
| District |
Idukki |
| Executing Office |
Peerumedu Sn |
| AS Amount (Rs) |
6235000
|
| AS Number |
RBI2302451134952 |
| TS Amount (Rs) |
6052000 |
| TS Number |
12861/2024-2025 |
| Total Bill Submitted (Rs) |
0 |
| Total Bill Paid (Rs) |
0 |
| Population Benefitted |
250 |
| Capacity in MLD |
9.50 |
| Actual Project Completion Date |
Date is not specified |
| Coverage |
from 4th Mile towards Chinnar area |
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
DEPOSIT-Relaying of Damaged existing pipe from 4th Mile towards Chinnar area on PWD Road-2023-24-Pipeline Work |
Peerumedu Sn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 03 Jul 2025 |
Compleated |
Peerumedu Sn AE |
|
| 15 Jan 2025 |
Work started |
Peerumedu Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
22/10/2024 |
| Scheduled date of Completion of the Project |
21 Jan 2025 |
| Expected date of Completion |
21/01/2025 |
Processing Dates
| AS Date |
19 Aug 2024 |
| TS Date |
09 Sep 2024 |