Jal Jeevan Mission (JJM)-Phase IV -WSS to Kidangoor, Kadaplamattom and Marangattupally Panchayaths - Marangattupalli Panchayath

Project Jal Jeevan Mission (JJM)-Phase IV -WSS to Kidangoor, Kadaplamattom and Marangattupally Panchayaths - Marangattupalli Panchayath
Project Code KTMJJM022215954P1
Type Package
Main Project Jal Jeevan Mission (JJM)-Phase IV -WSS to Kidangoor, Kadaplamattom and Marangattupally Panchayaths - Construction of OHSRs, Laying Distribution net work and Providing FHTCs in Marangattupalli Panchayath.-General Civil Work
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-Phase IV -WSS to Kidangoor, Kadaplamattom and Marangattupally Panchayaths - Construction of OHSRs, Laying Distribution net work and Providing FHTCs in Marangattupalli Panchayath.-General Civil Work
Status On-going
District Kottayam
Executing Office Kaduthuruthy Sn
Agreement Number
Agreement Date
TS Amount (Rs) 453860000
TS Number WRD/KWA-CE(SR)/EST_TS/13162/2022_5_2_1
Technical specification
Contractor SHONEY P JACOB (Mob: 9447677787)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 26/10/2023
Scheduled date of Completion as per agreement 25 Sep 2024
Expected date of Completion 25/09/2024

Processing Dates

TS Date 14 Jul 2023
Estimate Approval 22 Feb 2023
NIT Approval 15 Jul 2023
Tender Closing 07 Aug 2023

Approval Dates

Workorder Date 26 Oct 2023
NA 10 Nov 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kaduthuruthy Dn EE
Date: 28/06/2024

Work in progress | 1% Completed

No work.

Kaduthuruthy Dn EE
Date: 27/06/2024

Work in progress | 1% Completed

No work .