Jal Jeevan Mission (JJM)-Phase IV -WSS to Kidangoor, Kadaplamattom and Marangattupally Panchayaths - Construction of OHSRs, Laying Distribution net work and Providing FHTCs in Marangattupalli Panchayath.-General Civil Work

Project Jal Jeevan Mission (JJM)-Phase IV -WSS to Kidangoor, Kadaplamattom and Marangattupally Panchayaths - Construction of OHSRs, Laying Distribution net work and Providing FHTCs in Marangattupalli Panchayath.-General Civil Work
Project Code KTMJJM022215954
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-Phase IV -WSS to Kidangoor, Kadaplamattom and Marangattupally Panchayaths - Construction of OHSRs, Laying Distribution net work and Providing FHTCs in Marangattupalli Panchayath.-General Civil Work
Status On-going
District Kottayam
Executing Office Kaduthuruthy PH Sub Dn
AS Amount (Rs) 2112997000
AS Number GO(Rt) No 134/2022/WRD
TS Amount (Rs) 453860000
TS Number WRD/KWA-CE(SR)/EST_TS/13162/2022_5_2_1
Total Bill Submitted (Rs) 25798993
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage Jal Jeevan Mission (JJM)-Phase IV -WSS to Kidangoor, Kadaplamattom and Marangattupally Panchayaths

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-Phase IV -WSS to Kidangoor, Kadaplamattom and Marangattupally Panchayaths - Marangattupalli Panchayath Kaduthuruthy Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Jun 2024 No work Kaduthuruthy Dn EE
25 Jun 2024 No work Kaduthuruthy Dn EE
24 Jun 2024 No work Kaduthuruthy Dn EE
23 Jun 2024 No work Kaduthuruthy Dn EE
22 Jun 2024 Preparation for pressure test work on 90mm PVC CL 4 at kumbamkondu maniyakupara road (ward2), Laying 90 mm PVC CL4 at Elavanal-Vallomkunnel rd Kaduthuruthy Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 26/10/2023
Scheduled date of Completion of the Project 25 Sep 2024
Expected date of Completion Date is not specified

Processing Dates

AS Date 23 Feb 2022
TS Date 14 Jul 2023

Other details

Project Officers View