Jal Jeevan Mission (JJM)-Phase IV -WSS to Kidangoor, Kadaplamattom and Marangattupally Panchayaths - Construction of OHSRs, Laying Distribution net work and Providing FHTCs in Marangattupalli Panchayath.-General Civil Work
Project |
Jal Jeevan Mission (JJM)-Phase IV -WSS to Kidangoor, Kadaplamattom and Marangattupally Panchayaths - Construction of OHSRs, Laying Distribution net work and Providing FHTCs in Marangattupalli Panchayath.-General Civil Work |
Project Code |
KTMJJM022215954 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission (JJM)-Phase IV -WSS to Kidangoor, Kadaplamattom and Marangattupally Panchayaths - Construction of OHSRs, Laying Distribution net work and Providing FHTCs in Marangattupalli Panchayath.-General Civil Work
|
Status |
On-going |
District |
Kottayam |
Executing Office |
Kaduthuruthy PH Sub Dn |
AS Amount (Rs) |
2112997000
|
AS Number |
GO(Rt) No 134/2022/WRD |
TS Amount (Rs) |
453860000 |
TS Number |
WRD/KWA-CE(SR)/EST_TS/13162/2022_5_2_1 |
Total Bill Submitted (Rs) |
25798993 |
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
Jal Jeevan Mission (JJM)-Phase IV -WSS to Kidangoor, Kadaplamattom and Marangattupally Panchayaths |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)-Phase IV -WSS to Kidangoor, Kadaplamattom and Marangattupally Panchayaths - Marangattupalli Panchayath |
Kaduthuruthy Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
26 Jun 2024 |
No work |
Kaduthuruthy Dn EE |
|
25 Jun 2024 |
No work |
Kaduthuruthy Dn EE |
|
24 Jun 2024 |
No work |
Kaduthuruthy Dn EE |
|
23 Jun 2024 |
No work |
Kaduthuruthy Dn EE |
|
22 Jun 2024 |
Preparation for pressure test work on 90mm PVC CL 4 at kumbamkondu maniyakupara road (ward2), Laying 90 mm PVC CL4 at Elavanal-Vallomkunnel rd |
Kaduthuruthy Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
26/10/2023 |
Scheduled date of Completion of the Project |
25 Sep 2024 |
Expected date of Completion |
Date is not specified |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
14 Jul 2023 |