Project | KIIFB 2016-17-WRD 002-07- WSS to koyilandy muncipality and adjoining panchayath (phase1)-Package1 |
---|---|
Project Code | CLTKIIFB1117507P1 |
Type | Package |
Main Project | KIIFB-2016-17-WRD 002-07- WSS to koyilandy muncipality and adjoining panchayath (phase1) |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | Laying transmission main from Kayanna to Uralloor and renovation of GLSR at kottoor |
Status | On-going |
District | Kozhikkode |
Executing Office | Kozhikode Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 374500000 |
TS Number | KWA/CE/NR/31/2016-17 |
Technical specification | Laying transmission main from kayanna to Urallor AND Kottoor (900mm-5530m,800mm-2545m,600mm-6780m,500mm-100m,200mm-1616m) --16110 m and Improvements to existing 5LL GLSR at Kottoor G.P |
Contractor | REENA ENGINEERS & CONTRACTORS PVT LTD (Mob: 9544144862) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 07/07/2018 |
---|---|
Scheduled date of Completion as per agreement | 06 Sep 2019 |
Expected date of Completion | 30/09/2020 |
TS Date | 09 Feb 2017 |
---|---|
Estimate Approval | 09 Feb 2017 |
NIT Approval | 23 Jan 2017 |
Tender Closing | 21 Mar 2017 |
Technichal Pre-Qualification | 03 Apr 2017 |
Price bid opening | 25 Mar 2017 |
Workorder Date | 07 Jul 2018 |
---|---|
NA | 09 Jul 2018 |
Kozhikode Project Dn AE5 |
Date: 14/01/2022 |
Work has been completed | 100% Completed
Work completed. Total expenditure Rs.325273720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges.CC 9th and Final bill submitted on 14.01.2022..
Kozhikode Project Dn AE5 |
Date: 01/12/2021 |
Work has been completed | 100% Completed
Work completed. Total expenditure Rs.325013720/- CC 9th and part bill Differential Tax (-GST) paid to contractor on 24-06-2021 including Road restoration charges..