JAL JEEVAN MISSION - Phase I (2020-22) - CWSS to Thevalakara Thekkumbhagom - Supply and Laying Distribution lines - DI, MS, PVC, GI, HDPE pipes of various size as per design provided, Providing FHTC (2388 Nos.), Construction of Tube well, Supply of Standby Submersible pump sets, Installation of Bulk Water Meters etc. in Thekkumbhagam Panchayat.

Project JAL JEEVAN MISSION - Phase I (2020-22) - CWSS to Thevalakara Thekkumbhagom - Supply and Laying Distribution lines - DI, MS, PVC, GI, HDPE pipes of various size as per design provided, Providing FHTC (2388 Nos.), Construction of Tube well, Supply of Standby Submersible pump sets, Installation of Bulk Water Meters etc. in Thekkumbhagam Panchayat.
Project Code KLMJJM082010664P1
Type Package
Main Project JAL JEEVAN MISSION - Phase I (2020-22) - CWSS to Thevalakara Thekkumbhagom - Supply and Laying Distribution lines - DI, MS, PVC, GI, HDPE pipes of various size as per design provided, Providing FHTC (2388 Nos.), Construction of Tube well, Supply of Standby Submersible pump sets, Installation of Bulk Water Meters etc. in Thekkumbhagam Panchayat.
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JAL JEEVAN MISSION - Phase I (2020-22) - CWSS to Thevalakara Thekkumbhagom - Supply and Laying Distribution lines - DI, MS, PVC, GI, HDPE pipes of various size as per design provided, Providing FHTC (2388 Nos.), Construction of Tube well, Supply of Standby Submersible pump sets, Installation of Bulk Water Meters etc. in Thekkumbhagam Panchayat.
Status On-going
District Kollam
Executing Office Chavara PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 106000000
TS Number 13797/2021-2022
Technical specification CWSS to Thevalakara Thekkumbhagom - Supply and Laying Distribution lines - DI, MS, PVC, GI, HDPE pipes of various size as per design provided, Providing FHTC (2388 Nos.), Construction of Tube well, Supply of Standby Submersible pump sets, Installation of Bulk Water Meters etc. in Thekkumbhagam Panchayat.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 25/03/2022
Scheduled date of Completion as per agreement 25 Mar 2023
Expected date of Completion 25/03/2023

Processing Dates

TS Date 24 Nov 2021
Estimate Approval 24 Nov 2021
NIT Approval 25 Nov 2021
Tender Closing 20 Dec 2021
Technichal Pre-Qualification 20 Dec 2021
Price bid opening 23 Dec 2022

Approval Dates

Workorder Date 10 Mar 2022
NA 25 Mar 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chavara AE
Date: 29/06/2024

Work in progress | 98% Completed

43800m laying completed out of 44000m,1537 connections completed out of 2388 connections. 15th and part bill submitted. .

Chavara AE
Date: 26/06/2024

Work in progress | 98% Completed

43800m laying completed,1537 connections completed, 15th and part bill submitted..