- Home
- JAL JEEVAN MISSION - Phase I (2020-22) -...
JAL JEEVAN MISSION - Phase I (2020-22) - CWSS to Thevalakara Thekkumbhagom - Supply and Laying Distribution lines - DI, MS, PVC, GI, HDPE pipes of various size as per design provided, Providing FHTC (2388 Nos.), Construction of Tube well, Supply of Standby Submersible pump sets, Installation of Bulk Water Meters etc. in Thekkumbhagam Panchayat.
Project |
JAL JEEVAN MISSION - Phase I (2020-22) - CWSS to Thevalakara Thekkumbhagom - Supply and Laying Distribution lines - DI, MS, PVC, GI, HDPE pipes of various size as per design provided, Providing FHTC (2388 Nos.), Construction of Tube well, Supply of Standby Submersible pump sets, Installation of Bulk Water Meters etc. in Thekkumbhagam Panchayat. |
Project Code |
KLMJJM082010664P1 |
Type |
Package |
Main Project |
JAL JEEVAN MISSION - Phase I (2020-22) - CWSS to Thevalakara Thekkumbhagom - Supply and Laying Distribution lines - DI, MS, PVC, GI, HDPE pipes of various size as per design provided, Providing FHTC (2388 Nos.), Construction of Tube well, Supply of Standby Submersible pump sets, Installation of Bulk Water Meters etc. in Thekkumbhagam Panchayat.
|
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JAL JEEVAN MISSION - Phase I (2020-22) - CWSS to Thevalakara Thekkumbhagom - Supply and Laying Distribution lines - DI, MS, PVC, GI, HDPE pipes of various size as per design provided, Providing FHTC (2388 Nos.), Construction of Tube well, Supply of Standby Submersible pump sets, Installation of Bulk Water Meters etc. in Thekkumbhagam Panchayat. |
Status |
On-going |
District |
Kollam |
Executing Office |
Chavara PH Sn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
106000000 |
TS Number |
13797/2021-2022 |
Technical specification |
CWSS to Thevalakara Thekkumbhagom - Supply and Laying Distribution lines - DI, MS, PVC, GI, HDPE pipes of various size as per design provided, Providing FHTC (2388 Nos.), Construction of Tube well, Supply of Standby Submersible pump sets, Installation of Bulk Water Meters etc. in Thekkumbhagam Panchayat. |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
25/03/2022 |
Scheduled date of Completion as per agreement |
25 Mar 2023 |
Expected date of Completion |
25/03/2023 |
Processing Dates
TS Date |
24 Nov 2021 |
Estimate Approval |
24 Nov 2021 |
NIT Approval |
25 Nov 2021 |
Tender Closing |
20 Dec 2021 |
Technichal Pre-Qualification |
20 Dec 2021 |
Price bid opening |
23 Dec 2022 |
Approval Dates
Workorder Date |
10 Mar 2022 |
NA |
25 Mar 2022 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Chavara AE |
Date: 29/06/2024 |
Work in progress | 98% Completed
43800m laying completed out of 44000m,1537 connections completed out of 2388 connections. 15th and part bill submitted. .
Chavara AE |
Date: 26/06/2024 |
Work in progress | 98% Completed
43800m laying completed,1537 connections completed, 15th and part bill submitted..