Project | JJM- 3rd SLSSC-Kallooppara Grama Panchayath (Final Phase- Package 1) Providing 3201 FHTCs and replacing old and damaged pipe lines including road restoration works |
---|---|
Project Code | PTAJJM092114972P1 |
Type | Package |
Main Project | JJM- 3rd SLSSC-Kallooppara Grama Panchayath (Final Phase- Package 1) Providing 3201 FHTCs and replacing old and damaged pipe lines including road restoration works |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM- 3rd SLSSC-Kallooppara Grama Panchayath (Final Phase- Package 1) Providing 3201 FHTCs and replacing old and damaged pipe lines including road restoration works |
Status | On-going |
District | Pathanamthitta |
Executing Office | Mallappally Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 97900000 |
TS Number | WRD/KWA-CE(SR)/EST_TS/10242/2022_26_2_1 |
Technical specification | FHTCs |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 18/09/2021 |
---|---|
Scheduled date of Completion as per agreement | 04 Jun 2024 |
Expected date of Completion | 04/06/2024 |
TS Date | 29 Jun 2023 |
---|---|
Estimate Approval | 29 Jun 2023 |
NIT Approval | 29 Jun 2023 |
Tender Closing | 21 Jul 2023 |
Technichal Pre-Qualification | 07 Aug 2023 |
Price bid opening | 08 Aug 2023 |
Workorder Date | 11 Aug 2023 |
---|---|
NA | 05 Sep 2023 |
Mallappally PH Sn - AE |
Date: 27/06/2024 |
Work in progress | 18% Completed
160 mm PVC -510m layed, 140mm PVC -780m layed & 90mm PVC -2488m ,110mm PVC-1106m layed. Total No.of connections gived:268 connections. No.of Connections Geo tagged & IMIS Completed 256..
Mallappally PH Sn - AE |
Date: 24/06/2024 |
Work in progress | 18% Completed
160 mm PVC -510m layed, 140mm PVC -780m layed & 90mm PVC -2488m ,110mm PVC-1106m layed. Total No.of connections gived:268 connections. No.of Connections Geo tagged & IMIS Completed 256.