JJM- 3rd SLSSC-Kallooppara Grama Panchayath (Final Phase- Package 1) Providing 3201 FHTCs and replacing old and damaged pipe lines including road restoration works
Project |
JJM- 3rd SLSSC-Kallooppara Grama Panchayath (Final Phase- Package 1) Providing 3201 FHTCs and replacing old and damaged pipe lines including road restoration works |
Project Code |
PTAJJM092114972 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM- 3rd SLSSC-Kallooppara Grama Panchayath (Final Phase- Package 1) Providing 3201 FHTCs and replacing old and damaged pipe lines including road restoration works |
Status |
On-going |
District |
Pathanamthitta |
Executing Office |
Thiruvalla PH Dn |
AS Amount (Rs) |
242600000
|
AS Number |
GO(Rt)No.489/2021/WRD |
TS Amount (Rs) |
97900000 |
TS Number |
WRD/KWA-CE(SR)/EST_TS/10242/2022_26_2_1 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
6800 |
Capacity in MLD |
0.68 |
Actual Project Completion Date |
04 Jun 2024 |
Coverage |
FHTCs given |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM- 3rd SLSSC-Kallooppara Grama Panchayath (Final Phase- Package 1) Providing 3201 FHTCs and replacing old and damaged pipe lines including road restoration works |
Mallappally Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
24 Jun 2024 |
160 mm PVC -510m layed, 140mm PVC -780m layed & 90mm PVC -2488m ,110mm PVC-1106m layed. Total No.of connections gived:268 connections. No.of Connections Geo tagged & IMIS Completed 256 |
Mallappally PH Sn - AE |
|
22 Jun 2024 |
160 mm PVC -510m layed, 140mm PVC -780m layed & 90mm PVC -2488m ,110mm PVC-1106m layed. Total No.of connections gived:268 connections. No.of Connections Geo tagged & IMIS Completed 256 |
Mallappally PH Sn - AE |
|
20 Jun 2024 |
160 mm PVC -510m layed, 140mm PVC -780m layed & 90mm PVC -2488m ,110mm PVC-1106m layed. Total No.of connections gived:268 connections. No.of Connections Geo tagged & IMIS Completed 256 View all updates |
Mallappally PH Sn - AE |
|
18 Jun 2024 |
160 mm PVC -510m layed, 140mm PVC -780m layed & 90mm PVC -2488m ,110mm PVC-1106m layed. Total No.of connections gived:268 connections. No.of Connections Geo tagged & IMIS Completed 256 View all updates |
Mallappally PH Sn - AE |
|
15 Jun 2024 |
160 mm PVC -510m layed, 140mm PVC -780m layed & 90mm PVC -2488m ,110mm PVC-1106m layed. Total No.of connections gived:268 connections. No.of Connections Geo tagged & IMIS Completed:228
|
Mallappally PH Sn - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
18/09/2021 |
Scheduled date of Completion of the Project |
04 Jun 2024 |
Expected date of Completion |
30/06/2024 |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
29 Jun 2023 |