Project | JJM - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 7LL OHSR at Padalikkadu school compound and 11LL OHSR at JTS compound in Marutharoad panchayath - Zone 7 and 8 |
---|---|
Project Code | PKDJJM12206095P1 |
Type | Package |
Main Project | JJM - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 7LL OHSR at Padalikkadu school compound and 11LL OHSR at JTS compound in Marutharoad panchayath - Zone 7 and 8 |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 7LL OHSR at Padalikkadu school compound and 11LL OHSR at JTS compound in Marutharoad panchayath - Zone 7 and 8 |
Status | On-going |
District | Palakkad |
Executing Office | Chittur Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 147400000 |
TS Number | TS/2020-2021/2020/2260 |
Technical specification | JJM - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 7LL OHSR at Padalikkadu school compound and 11LL OHSR at JTS compound in Marutharoad panchayath - Zone 7 and 8 |
Contractor | David Mangan (Mob: 9400592878) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 12/05/2021 |
---|---|
Scheduled date of Completion as per agreement | 11 Oct 2021 |
Expected date of Completion | 31/12/2024 |
TS Date | 01 Jan 2021 |
---|---|
Estimate Approval | 01 Jan 2021 |
NIT Approval | 01 Jan 2021 |
Tender Closing | 25 Mar 2021 |
Technichal Pre-Qualification | 07 May 2021 |
Price bid opening | 07 May 2021 |
Workorder Date | 12 May 2021 |
---|---|
NA | 01 Jun 2021 |
Chittur Project Dn - AE 2 |
Date: 27/06/2024 |
Work in progress | 82% Completed
Supplied total -84.753km, Laid Total-74KM,/out of 90km , HTC -2499 out of 4422Nos 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --68628m . Pipe Laid length. 1).110mm PVC—7.757k m 2).90mm PVC—195.6006km, 3). 140mm pvc-2.105 4).160mm PVC,6kg—2.390 km 5)250mm DI K9-1946.80 m 6).350mm DI K9-210m 7) 200mm DI-300M, 8)300 mm DI-118M 9)125mm DI-12M 10)400 mm DI-6M (4th bill-170 FHTC provided).
Chittur Project Dn - AE 2 |
Date: 20/06/2024 |
Work in progress | 82% Completed
Supplied total -84.753km, Laid Total-74KM,/out of 90km , HTC -2499 out of 4422Nos 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --68628m . Pipe Laid length. 1).110mm PVC—7.757k m 2).90mm PVC—195.6006km, 3). 140mm pvc-2.105 4).160mm PVC,6kg—2.390 km 5)250mm DI K9-1946.80 m 6).350mm DI K9-210m 7) 200mm DI-300M, 8)300 mm DI-118M 9)125mm DI-12M 10)400 mm DI-6M (4th bill-170 FHTC provided).