JJM - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 7LL OHSR at Padalikkadu school compound and 11LL OHSR at JTS compound in Marutharoad panchayath - Zone 7 and 8

Project JJM - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 7LL OHSR at Padalikkadu school compound and 11LL OHSR at JTS compound in Marutharoad panchayath - Zone 7 and 8
Project Code PKDJJM12206095P1
Type Package
Main Project JJM - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 7LL OHSR at Padalikkadu school compound and 11LL OHSR at JTS compound in Marutharoad panchayath - Zone 7 and 8
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 7LL OHSR at Padalikkadu school compound and 11LL OHSR at JTS compound in Marutharoad panchayath - Zone 7 and 8
Status On-going
District Palakkad
Executing Office Chittur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 147400000
TS Number TS/2020-2021/2020/2260
Technical specification JJM - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 7LL OHSR at Padalikkadu school compound and 11LL OHSR at JTS compound in Marutharoad panchayath - Zone 7 and 8
Contractor David Mangan (Mob: 9400592878)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 12/05/2021
Scheduled date of Completion as per agreement 11 Oct 2021
Expected date of Completion 31/12/2024

Processing Dates

TS Date 01 Jan 2021
Estimate Approval 01 Jan 2021
NIT Approval 01 Jan 2021
Tender Closing 25 Mar 2021
Technichal Pre-Qualification 07 May 2021
Price bid opening 07 May 2021

Approval Dates

Workorder Date 12 May 2021
NA 01 Jun 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chittur Project Dn - AE 2
Date: 27/06/2024

Work in progress | 82% Completed

Supplied total -84.753km, Laid Total-74KM,/out of 90km , HTC -2499 out of 4422Nos 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --68628m . Pipe Laid length. 1).110mm PVC—7.757k m 2).90mm PVC—195.6006km, 3). 140mm pvc-2.105 4).160mm PVC,6kg—2.390 km 5)250mm DI K9-1946.80 m 6).350mm DI K9-210m 7) 200mm DI-300M, 8)300 mm DI-118M 9)125mm DI-12M 10)400 mm DI-6M (4th bill-170 FHTC provided).

Chittur Project Dn - AE 2
Date: 20/06/2024

Work in progress | 82% Completed

Supplied total -84.753km, Laid Total-74KM,/out of 90km , HTC -2499 out of 4422Nos 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --68628m . Pipe Laid length. 1).110mm PVC—7.757k m 2).90mm PVC—195.6006km, 3). 140mm pvc-2.105 4).160mm PVC,6kg—2.390 km 5)250mm DI K9-1946.80 m 6).350mm DI K9-210m 7) 200mm DI-300M, 8)300 mm DI-118M 9)125mm DI-12M 10)400 mm DI-6M (4th bill-170 FHTC provided).