Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 7LL OHSR at Padalikkadu school compound and 11LL OHSR at JTS compound in Marutharoad panchayath - Zone 7 and 8

Project JJM - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 7LL OHSR at Padalikkadu school compound and 11LL OHSR at JTS compound in Marutharoad panchayath - Zone 7 and 8
Project Code PKDJJM12206095P1
Type Package
Main Project JJM - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 7LL OHSR at Padalikkadu school compound and 11LL OHSR at JTS compound in Marutharoad panchayath - Zone 7 and 8
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Description JJM - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 7LL OHSR at Padalikkadu school compound and 11LL OHSR at JTS compound in Marutharoad panchayath - Zone 7 and 8
Status On-going
District Palakkad
Executing Office Chittur Project Dn
TS Amount (Rs) 147400000
TS Number TS/2020-2021/2020/2260
Technical specification JJM - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 7LL OHSR at Padalikkadu school compound and 11LL OHSR at JTS compound in Marutharoad panchayath - Zone 7 and 8

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 12/05/2021
Scheduled date of Completion as per agreement 11 Oct 2021
Expected date of Completion 11/10/2021

Processing Dates

TS Date 01 Jan 2021
Estimate Approval 01 Jan 2021
NIT Approval 01 Jan 2021
Tender Closing 25 Mar 2021
Technichal Pre-Qualification 07 May 2021
Price bid opening 07 May 2021

Approval Dates

Workorder Date 12 May 2021
Agreement Date 31 May 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Location

Project Status Updations See All Status Updations

Chittur Project Dn - AE 2
Date: 24/07/2021

Work in progress | 3% Completed

90mm pvc 6 kg-24996.00 m supplied at site and 8500m laid.

Chittur Project Dn - AE 2
Date: 20/07/2021

Work in progress | 3% Completed

90mm pvc 6 kg-24996.00 m supplied at site and 7800m laid.