JJM 2021 – 22 –Setting up/ upgradation / Operation of laboratories – NABL Accreditation of Sub District Laboratory at Thodupuzha

Project JJM 2021 – 22 –Setting up/ upgradation / Operation of laboratories – NABL Accreditation of Sub District Laboratory at Thodupuzha
Project Code IDKJJM09218450
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description NABL Accreditation of Sub District Laboratory at Thodupuzha
Status Completed
District Idukki
Executing Office Idukki QC Sn
AS Amount (Rs) 838600000
AS Number 489/2021/WRD
TS Amount (Rs) 1870000
TS Number TS/2021-2022/2021/28788
Total Bill Submitted (Rs) 1461739
Total Bill Paid (Rs) 1331228
Population Benefitted 400000
Capacity in MLD
Actual Project Completion Date 21 Mar 2022
Coverage

Packages

No. Project Name Location View
1 JJM 2021 – 22 –Setting up/ upgradation / Operation of laboratories – NABL Accreditation of Sub District Laboratory at Thodupuzha Idukki QC Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 Jul 2022 Work completed .Final bill under preparation. Idukki QCDL - AE
03 Feb 2022 85% work finished. Idukki QCDL - AE
21 Jan 2022 71% work completed. Idukki QCDL - AE
10 Jan 2022 58 % completed Idukki QCDL - AE
05 Jan 2022 50 % completed Kochi QC Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 24/11/2021
Scheduled date of Completion of the Project 23 Dec 2021
Expected date of Completion 20/01/2022

Processing Dates

AS Date 18 Sep 2021
TS Date 20 Oct 2021

Other details

Project Officers View