| Project | JJM 2021 – 22 –Setting up/ upgradation / Operation of laboratories – NABL Accreditation of Sub District Laboratory at Thodupuzha |
|---|---|
| Project Code | IDKJJM09218450P1 |
| Type | Package |
| Main Project | JJM 2021 – 22 –Setting up/ upgradation / Operation of laboratories – NABL Accreditation of Sub District Laboratory at Thodupuzha |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | NABL Accreditation of Sub District Laboratory at Thodupuzha |
| Status | Completed |
| District | Idukki |
| Executing Office | Idukki QC Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 1664462 |
| TS Number | TS/2021-2022/2021/28788 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 01/12/2021 |
|---|---|
| Scheduled date of Completion as per agreement | 23 Dec 2021 |
| Expected date of Completion | 24/03/2022 |
| TS Date | 20 Oct 2021 |
|---|---|
| Estimate Approval | 20 Oct 2021 |
| NIT Approval | 20 Oct 2021 |
| Tender Closing | 04 Nov 2021 |
| Technichal Pre-Qualification | 06 Nov 2021 |
| Price bid opening | 07 Jul 2022 |
| Workorder Date | 24 Nov 2021 |
|---|---|
| NA | 01 Dec 2021 |
| Idukki QCDL - AE |
| Date: 24/06/2022 |
Work has been completed | 100% Completed
work completed ,Final bill under prepration..
| Idukki QCDL - AE |
| Date: 25/03/2022 |
Work in progress | 98% Completed
98 % work completed .Part bill submitted ..