Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Budget -2017-2018-KIIFB project-TRAN10:WRD 025-13-WSS to Ramanchadi- Aligarh in Malappuram District- Package 4 construction of weir

Project Budget -2017-2018-KIIFB project-TRAN10:WRD 025-13-WSS to Ramanchadi- Aligarh in Malappuram District- Package 4 construction of weir
Project Code MLPKIIFB1118510P7
Type Package
Main Project Budget -2017-2018-KIIFB project-TRAN10:WRD 025-13-WSS to Ramanchadi- Aligarh in Malappuram District
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description This package is for the construction of weir
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
Agreement Number
Agreement Date
TS Amount (Rs)
TS Number
Technical specification Due to public protest, we are unable to construct the weir on the previous location. Hence after several communications and meetings, new location got proposed. Now we we are proceeding with the survey, estimate.. etc.. For the construction of new weir

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 31/05/2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malappuram Project Dn AE3
Date: 03/05/2024

Work has started | 0% Completed

As per the joint meeting with CE irrigation with our CE,it is decided to deposit weir AS amount 2.9 crore rupees in the Irrigation project. Irrigation dept is progressing towards AS for their project. In joint meeting with CE irrigation and CR IDRB conducted on 11/04/2022, CE IDRB informed that the design will be ready soon. Direction was given by Secretary to Government, Water Resources (WS-C) Department to CE (I&A) to prepare a submite DPR of the subject work for Administrative Saction on 19/08/2023 .

Malappuram Project Dn AE3
Date: 02/05/2024

Work has started | 0% Completed

As per the joint meeting with CE irrigation with our CE,it is decided to deposit weir AS amount 2.9 crore rupees in the Irrigation project. Irrigation dept is progressing towards AS for their project. In joint meeting with CE irrigation and CR IDRB conducted on 11/04/2022, CE IDRB informed that the design will be ready soon. Direction was given by Secretary to Government, Water Resources (WS-C) Department to CE (I&A) to prepare a submite DPR of the subject work for Administrative Saction on 19/08/2023 .