Jal Jeevan Mission (JJM)-JJM PHASE 2- 2021-22 WSS to Desamangalam, Varavoor, Erumapetty, Kadangode, Velur ,Choondal,Kandanassery,Mullurkara Part(W-1,2,3,4,half of 5 and 14) Panchayaths & Wadakkanchery Muncipality -Package I --Construction of 12m Dia intake well at Kondayur -General Civil Work-
Project |
Jal Jeevan Mission (JJM)-JJM PHASE 2- 2021-22 WSS to Desamangalam, Varavoor, Erumapetty, Kadangode, Velur ,Choondal,Kandanassery,Mullurkara Part(W-1,2,3,4,half of 5 and 14) Panchayaths & Wadakkanchery Muncipality -Package I --Construction of 12m Dia intake well at Kondayur -General Civil Work- |
Project Code |
TCRJJM052215568 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Construction of 12m Dia intake well at Kondayur |
Status |
On-going |
District |
Thrissur |
Executing Office |
Nattika Project Dn |
AS Amount (Rs) |
4497130000
|
AS Number |
G.O.(Rt) No.401/2022/WRD |
TS Amount (Rs) |
101900000 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/11070/2023_5_1_1 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
32483 |
Capacity in MLD |
40.00 |
Actual Project Completion Date |
19 Jun 2024 |
Coverage |
12 m dia Intake well |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)-JJM PHASE 2- 2021-22 WSS to Desamangalam, Varavoor, Erumapetty, Kadangode, Velur ,Choondal,Kandanassery,Mullurkara Part(W-1,2,3,4,half of 5 and 14) Panchayaths & Wadakkanchery Muncipality -Package I --Construction of 12m Dia intake well at Kondayur -General Civil Work- |
Nattika Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
14 Mar 2024 |
work not started |
Nattika Project Dn |
|
06 Mar 2024 |
work not started |
Nattika Project Dn |
|
16 Feb 2024 |
4.3 km pipe supplied |
Nattika Project Dn |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
20/09/2023 |
Scheduled date of Completion of the Project |
19 Jun 2024 |
Expected date of Completion |
18/06/2024 |
Processing Dates
AS Date |
13 May 2022 |
TS Date |
04 Aug 2023 |