KIIFB: CWSS to Pulimath, Nagaroor & Karavaram Panchayaths - Phase-I, (Package -1,2,3,4,5,6 and 7) - Construction of 9mWell cum pump house, Raw water pumping main, 18 MLD WTP and allied items, transformer at well site, raw water pump sets, OHSRs, Sump, Road restoration and Clear water pumping main

Project KIIFB: CWSS to Pulimath, Nagaroor & Karavaram Panchayaths - Phase-I, (Package -1,2,3,4,5,6 and 7) - Construction of 9mWell cum pump house, Raw water pumping main, 18 MLD WTP and allied items, transformer at well site, raw water pump sets, OHSRs, Sump, Road restoration and Clear water pumping main
Project Code TVMKIIFB0219618P3
Type Package
Main Project KIIFB : CWSS to Pulimath,Nagaroor and Karavaram Panchayaths Phase I
Funding Agency KIIFB
Category KIIFB WATER SUPPLY SCHEME
Type of scheme Water Supply
Scheme KIIFB
Description Construction of 9m well cum pumphouse at Anakudy, Supplying,laying,jointing,testing and commissioning of 500mmDI K9 Raw water pumping main, Design, construction, commissioning and maintenance of 18MLD WTP, Pumps, Motors, Electronic flow meter, substation building, water supply &electrical items in WTP, Supplying, Laying, Testing and Commissioning of clear water transmission mains:10930 metre-450mm DI K9 gravity main from treatment plant at Kuttimoodu to Nagaroor Jn. 1782 metre-400mm DI K9 pipe from Nagaroor Jn to OHSR at Paramukku, 3478metre-400mm DI K9 pipe from Nagaroor Jn to OHSR at Nellikunnu, Nedumparambu. Clear water pumping main 1775metre-150mm DI K9 pumping main from WTP Kuttimoodu to OHSR at Kadalkanipara & Supplying, laying, testing and commissioning of 4759m-200mm DI K9 Gravity main from Nedumparambu to Sump at Pavalla, 1751m 200mm DI K9 clear water pumping main from sump at Pavalla to OHSR at Vadnithadam. Design Construction testing and commissioning of 0.65 LL Sump at Pavalla in Karavaram Panchayath & Construction of 15.3LL, 14LL,5.2LL,2.8LL OHSRs & Road Restoration Package for restoring PWD/NH/KSTP and Panchayath roads. & electrical arrangements, landscaping, Anganwadi building, lightning conductor, Clear water pumpsets, Indoor Transformer, Transformer Room and allied works.& Supply, erection,testing and commissioning of clear water pump sets of 350HP VT(2+1) 3 Nos and 1250 KVA Indoor transformer, transformer room and allied woks at Anakudy well site.
Status On-going
District Thiruvananthapuram
Executing Office Trivandrum Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 707816000
TS Number TS/2021-2022/2020/1628,3798,3805,8281,11901,, TS/2021-2022/2021/40770, 40771, 40775, 40778,41366
Technical specification Construction of 9m well cum pumphouse at Anakudy, Supplying,laying,jointing,testing and commissioning of 500mmDI K9 Raw water pumping main, Design, construction, commissioning and maintenance of 18MLD WTP, Pumps, Motors, Electronic flow meter, substation building, water supply &electrical items in WTP, Supplying, Laying, Testing and Commissioning of clear water transmission mains:10930 metre-450mm DI K9 gravity main from treatment plant at Kuttimoodu to Nagaroor Jn. 1782 metre-400mm DI K9 pipe from Nagaroor Jn to OHSR at Paramukku, 3478metre-400mm DI K9 pipe from Nagaroor Jn to OHSR at Nellikunnu, Nedumparambu. Clear water pumping main 1775metre-150mm DI K9 pumping main from WTP Kuttimoodu to OHSR at Kadalkanipara & Supplying, laying, testing and commissioning of 4759m-200mm DI K9 Gravity main from Nedumparambu to Sump at Pavalla, 1751m 200mm DI K9 clear water pumping main from sump at Pavalla to OHSR at Vadnithadam. Design Construction testing and commissioning of 0.65 LL Sump at Pavalla in Karavaram Panchayath & Construction of 15.3LL, 14LL,5.2LL,2.8LL OHSRs & Road Restoration Package for restoring PWD/NH/KSTP and Panchayath roads. & electrical arrangements, landscaping, Anganwadi building, lightning conductor, Clear water pumpsets, Indoor Transformer, Transformer Room and allied works.& Supply, erection,testing and commissioning of clear water pump sets of 350HP VT(2+1) 3 Nos and 1250 KVA Indoor transformer, transformer room and allied woks at Anakudy well site.
Contractor M/s Chicago Construction International (P) Ltd (Mob: 9447111906)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 01/01/2022
Scheduled date of Completion as per agreement 30 Jun 2024
Expected date of Completion 30/06/2024

Processing Dates

TS Date 25 Apr 2022
Estimate Approval 10 Feb 2022
NIT Approval 31 Jan 2022
Tender Closing 22 Feb 2022
Technichal Pre-Qualification 17 Sep 2022
Price bid opening 02 Aug 2022

Approval Dates

Workorder Date 01 Oct 2022
NA 04 Nov 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thiruvananthapuram Project AE3
Date: 23/04/2024

Work in progress | 62% Completed

Recycling tank of 18 MLD WTP at Kuttimoodu – 3RD Stage retaining wall footing concrete completed. Laying of 500mm transmission main ongoing in Kuttimoodu-Karette stretch. 14LL OHSR at Nellikkunnu – 3rd lift side wall shuttering work ongoing, 5.2LL OHSR at Vandithadam – Side wall 1st lift concrete completed. Concreting of 3RD Lift above ring beam of 9.0m well at Anakudy ongoing. Electro mechanical drawings - Mechanical drawings approved and revised electrical drawings are yet to be submitted by the contractor for approval..

Attached images

img img img img img img

Thiruvananthapuram Project AE3
Date: 18/04/2024

Work in progress | 62% Completed

Recycling tank of 18 MLD WTP at Kuttimoodu – 3RD Stage retaining wall footing concrete completed. Laying of 500mm transmission main ongoing in Kuttimoodu-Karette stretch. 14LL OHSR at Nellikkunnu – 3rd lift side wall shuttering work ongoing, 5.2LL OHSR at Vandithadam – Side wall 1st lift concrete completed. Concreting of 3RD Lift above ring beam of 9.0m well at Anakudy ongoing. Electro mechanical drawings - Mechanical drawings approved and revised electrical drawings are yet to be submitted by the contractor for approval. .

Attached images

img img img img img img img