JAL JEEVAN MISSION – 2020-21 Providing FHTC in Edamulakkal Grama Panchayath from existing scheme and extension during the period 2020-21

Project JAL JEEVAN MISSION – 2020-21 Providing FHTC in Edamulakkal Grama Panchayath from existing scheme and extension during the period 2020-21
Project Code KLMJJM08203670
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JAL JEEVAN MISSION – 2020-21 Providing FHTC in Edamulakkal Grama Panchayath from existing scheme and extension during the period 2020-21 -8895FHTCs
Status On-going
District Kollam
Executing Office Punalur PH Sub Dn
AS Amount (Rs) 214617000
AS Number G.O.RT 541/2020/WRD
TS Amount (Rs) 196644000
TS Number TS/2021-2022/2020/16493
Total Bill Submitted (Rs) 115841853
Total Bill Paid (Rs) 115841853
Population Benefitted 22004
Capacity in MLD 72.00
Actual Project Completion Date 31 Aug 2023
Coverage Providing FHTC in Edamulakkal Grama Panchayath from existing scheme and extension during the period 2020-21 -8895FHTCs
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JAL JEEVAN MISSION – 2020-21 Providing FHTC in Edamulakkal Grama Panchayath from existing scheme and extension during the period 2020-21 Project Code KLMJJM08203670 Punalur WS Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Jun 2024 Work in Progress Punalur WS Sn - AE
24 Jun 2024 Work in progress Punalur WS Sn - AE
21 Jun 2024 Work in progress Punalur WS Sn - AE
18 Jun 2024 Work in progress Punalur WS Sn - AE
15 Jun 2024 Work in progress Punalur WS Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 31/12/2021
Scheduled date of Completion of the Project 31 Aug 2023
Expected date of Completion 31/08/2023

Processing Dates

AS Date 21 Aug 2020
TS Date 08 Jun 2021