JAL JEEVAN MISSION – 2020-21 Providing FHTC in Edamulakkal Grama Panchayath from existing scheme and extension during the period 2020-21 Project Code KLMJJM08203670

Project JAL JEEVAN MISSION – 2020-21 Providing FHTC in Edamulakkal Grama Panchayath from existing scheme and extension during the period 2020-21 Project Code KLMJJM08203670
Project Code KLMJJM08203670P1
Type Package
Main Project JAL JEEVAN MISSION – 2020-21 Providing FHTC in Edamulakkal Grama Panchayath from existing scheme and extension during the period 2020-21
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JAL JEEVAN MISSION – 2020-21 Providing FHTC in Edamulakkal Grama Panchayath from existing scheme and extension during the period 2020-21 Project Code KLMJJM08203670
Status On-going
District Kollam
Executing Office Punalur WS Sn
Agreement Number
Agreement Date
TS Amount (Rs) 163500000
TS Number TS/2020-2021/2020/16494
Technical specification (1.) FHTCs 8895 (2) pipe line All 8 kg/cm250mm dia- 4km63mm dia - 6km 75 mm dia - 15km90mm dia - 15km110mm dia 8km160mm dia 5 km total = 53 km (3) GLSR at Malamel 25000 Liters for providing potable water to about 70 numbers elevated houses at Malamel (4) pump sets and transmission main 80mm GI medium class pumping main

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 31/12/2021
Scheduled date of Completion as per agreement 30 Jun 2023
Expected date of Completion 31/08/2023

Processing Dates

TS Date 20 Sep 2020
Estimate Approval 07 Jun 2021
NIT Approval 07 Jun 2021
Tender Closing 04 Dec 2020
Technichal Pre-Qualification 10 Jun 2021
Price bid opening 30 Aug 2021

Approval Dates

Workorder Date 30 Nov 2021
NA 31 Dec 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Punalur WS Sn - AE
Date: 26/06/2024

Work in progress | 89% Completed

Work in Progress.

Punalur WS Sn - AE
Date: 24/06/2024

Work in progress | 88% Completed

Work in progress.