Project | JAL JEEVAN MISSION – 2020-21 Providing FHTC in Edamulakkal Grama Panchayath from existing scheme and extension during the period 2020-21 Project Code KLMJJM08203670 |
---|---|
Project Code | KLMJJM08203670P1 |
Type | Package |
Main Project | JAL JEEVAN MISSION – 2020-21 Providing FHTC in Edamulakkal Grama Panchayath from existing scheme and extension during the period 2020-21 |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JAL JEEVAN MISSION – 2020-21 Providing FHTC in Edamulakkal Grama Panchayath from existing scheme and extension during the period 2020-21 Project Code KLMJJM08203670 |
Status | On-going |
District | Kollam |
Executing Office | Punalur WS Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 163500000 |
TS Number | TS/2020-2021/2020/16494 |
Technical specification | (1.) FHTCs 8895 (2) pipe line All 8 kg/cm250mm dia- 4km63mm dia - 6km 75 mm dia - 15km90mm dia - 15km110mm dia 8km160mm dia 5 km total = 53 km (3) GLSR at Malamel 25000 Liters for providing potable water to about 70 numbers elevated houses at Malamel (4) pump sets and transmission main 80mm GI medium class pumping main |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 31/12/2021 |
---|---|
Scheduled date of Completion as per agreement | 30 Jun 2023 |
Expected date of Completion | 31/08/2023 |
TS Date | 20 Sep 2020 |
---|---|
Estimate Approval | 07 Jun 2021 |
NIT Approval | 07 Jun 2021 |
Tender Closing | 04 Dec 2020 |
Technichal Pre-Qualification | 10 Jun 2021 |
Price bid opening | 30 Aug 2021 |
Workorder Date | 30 Nov 2021 |
---|---|
NA | 31 Dec 2021 |
Punalur WS Sn - AE |
Date: 26/06/2024 |
Work in progress | 89% Completed
Work in Progress.
Punalur WS Sn - AE |
Date: 24/06/2024 |
Work in progress | 88% Completed
Work in progress.