- Home
- Jal Jeevan Mission 2020-21 : Providing w...
Jal Jeevan Mission 2020-21 : Providing water connection from the existing WS schemes in Pazhayakunnummel Panchayath
Project |
Jal Jeevan Mission 2020-21 : Providing water connection from the existing WS schemes in Pazhayakunnummel Panchayath |
Project Code |
TVMJJM08208102 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission 2020-21 : Providing water connection from the existing WS schemes in Pazhayakunnummel Panchayath |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Attingal WS Dn |
AS Amount (Rs) |
62875000
|
AS Number |
GO(RT) no.541/2020/WRD Dated:21-08-2020 |
TS Amount (Rs) |
62871000 |
TS Number |
TS/2020-2021/2020/13908 Dated: 11-01-2021 |
Total Bill Submitted (Rs) |
1825697 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
10000 |
Capacity in MLD |
2.00 |
Actual Project Completion Date |
15 Sep 2022 |
Coverage |
70% |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission 2020-21 : Providing water connection from the existing WS schemes in Pazhayakunnummel Panchayath |
Attingal WS Sn 2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
03 Jun 2023 |
FHTCs work ongoing |
Attingal WS Sn no 2 - AE |
|
19 Apr 2023 |
2166 nos FHTCs given, work started after the sanction of Revised estimate, FHTCs work ongoing |
Attingal WS Sn no 2 - AE |
|
18 Nov 2022 |
Agreement executed for road cutting sanction from PWD |
Attingal WS Sn no 2 - AE |
|
07 Sep 2022 |
Agreement executed for road cutting sanction from PWD due to heavy rain work not continues |
Attingal WS Dn EE |
|
29 Aug 2022 |
Agreement executed for road cutting sanction from PWD |
Attingal WS Sn no 2 - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
15/10/2021 |
Scheduled date of Completion of the Project |
23 Mar 2022 |
Expected date of Completion |
31/08/2024 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
11 Jan 2021 |