Project Division Chittur KIIFB - 16-17 - Augmentation of Nenmara, Ayiloor and Melarcode in Chittur and Alathur Taluk in Palakkad District- Phase II- Package I - Design, construction and commissioning of 11.5 LL OHSR , RCC retaining wall including compound wall at Kaithachira in Ayiloor panchayath - Part 1

Project Project Division Chittur KIIFB - 16-17 - Augmentation of Nenmara, Ayiloor and Melarcode in Chittur and Alathur Taluk in Palakkad District- Phase II- Package I - Design, construction and commissioning of 11.5 LL OHSR , RCC retaining wall including compound wall at Kaithachira in Ayiloor panchayath - Part 1
Project Code PKDKIIFB1117627P2
Type Package
Main Project KIIFB - 16-17 - Augmentation of Nenmara, Ayiloor and Melarcode in Chittur and Alathur Taluk in Palakkad District- Phase II-
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description This project is for augmentation of the existing water supply scheme to Nenmara, Ayilur and Melarcode Panchayaths in Chittur and Alathur taluk. For the coverage of all habitations of three Panchayaths by utilizing perennial surface source of Pothundi irrigation Dam in Nemmara panchayath. The Package I and Package II is an ongoing project under WSP Project Division, Palakkad. The construction of 11.50 LL OHSR with staging height 3metre included in the Package I along with the laying of 450 mm DI K9 distribution main for a length of 1900m. The laying of distribution main completed. During the soil investigation work for the construction of OHSR it is seen that the site is unsuitable for the construction on removal of the boulders found at the site and site clearance. Hence alternate suitable land identified . . The component of 11.50 LL OHSR separately arranged as the contractor not carried out the construction of OHSR.
Status On-going
District Palakkad
Executing Office Chittur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 20200000
TS Number TS/2019-2020/2018/12947 dated 12-06-2019
Technical specification 1. construction of 11.50LL OHSR at Kaithachira in Ayiloor Panchayath 2. construction of RCC retaining wall including compound wall at kaithachira
Contractor k.k mohammed (Mob: 9447799272)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 11/10/2019
Scheduled date of Completion as per agreement 10 Oct 2020
Expected date of Completion 31/03/2022

Processing Dates

TS Date 12 Jun 2019
Estimate Approval 12 Jun 2019
NIT Approval 07 Aug 2019
Tender Closing 02 Sep 2019
Technichal Pre-Qualification 05 Sep 2019
Price bid opening 17 Sep 2019

Approval Dates

NA 23 Oct 2019
Workorder Date 11 Oct 2019

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chittur Project Dn - AE 3
Date: 31/05/2022

Work has been completed | 100% Completed

Work of OHSR has been completed.

Chittur Project Dn - AE 1
Date: 17/03/2022

Work has been completed | 100% Completed

Work of OHSR has been completed .