KIIFB - UWSS to Adoor and adj pt. (2215-01-190-94) 2018-19 - Replacement of 400 mm AC Transmission line and Distribution main by using 400mm DI K9 pipe from TP at Chiranikkal to Parakodu junction in Adoor municipality

Project KIIFB - UWSS to Adoor and adj pt. (2215-01-190-94) 2018-19 - Replacement of 400 mm AC Transmission line and Distribution main by using 400mm DI K9 pipe from TP at Chiranikkal to Parakodu junction in Adoor municipality
Project Code PTAKIIFB04186079P1
Type Package
Main Project KIIFB - UWSS to Adoor and adj pt. (2215-01-190-94) 2018-19 - Replacement of 400 mm AC Transmission line and Distribution main by using 400mm DI K9 pipe from TP at Chiranikkal to Parakodu junction in Adoor municipality
Funding Agency KIIFB
Category KIIFB WATER SUPPLY SCHEME
Type of scheme Water Supply
Scheme KIIFB
Description KIIFB - UWSS to Adoor and adj pt. (2215-01-190-94) 2018-19 - Replacement of 400 mm AC Transmission line and Distribution main by using 400mm DI K9 pipe from TP at Chiranikkal to Parakodu junction in Adoor municipality
Status On-going
District Pathanamthitta
Executing Office Chiranickal Sn
Agreement Number
Agreement Date
TS Amount (Rs) 56100000
TS Number APR -4/401/2018/KIIFB
Technical specification Replacement of 400 mm AC Transmission line and Distribution main by using 400mm DI K9 pipe from TP at Chiranikkal to Parakodu junction in Adoor municipality

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 31/12/2023

Processing Dates

TS Date 09 Mar 2023
Estimate Approval 09 Mar 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chiranickal WS Section - AE
Date: 05/03/2024

Work in progress | 1% Completed

work tendered . Only one participant. Bidder quoted 30 % above rate. Tender sanction to be obtained.

Chiranickal WS Section - AE
Date: 28/02/2024

Work in progress | 1% Completed

work tendered . Only one participant. Bidder quoted 30 % above rate. Tender sanction to be obtained.