- Home
- KIIFB - UWSS to Adoor and adj pt. (2215-...
KIIFB - UWSS to Adoor and adj pt. (2215-01-190-94) 2018-19 - Replacement of 400 mm AC Transmission line and Distribution main by using 400mm DI K9 pipe from TP at Chiranikkal to Parakodu junction in Adoor municipality
Project |
KIIFB - UWSS to Adoor and adj pt. (2215-01-190-94) 2018-19 - Replacement of 400 mm AC Transmission line and Distribution main by using 400mm DI K9 pipe from TP at Chiranikkal to Parakodu junction in Adoor municipality |
Project Code |
PTAKIIFB04186079 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
KIIFB WATER SUPPLY SCHEME |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
KIIFB - UWSS to Adoor and adj pt. (2215-01-190-94) 2018-19 - Replacement of 400 mm AC Transmission line and Distribution main by using 400mm DI K9 pipe from TP at Chiranikkal to Parakodu junction in Adoor municipality |
Status |
On-going |
District |
Pathanamthitta |
Executing Office |
Pathanamthitta PH Dn |
AS Amount (Rs) |
58896000
|
AS Number |
WRD005-123/APR-6/2022/KIIFB |
TS Amount (Rs) |
56100000 |
TS Number |
TS/2020-21/2018/986 |
Total Bill Submitted (Rs) |
27941876 |
Total Bill Paid (Rs) |
21012682 |
Population Benefitted |
30000 |
Capacity in MLD |
12.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Parakodu in Adoor municipality |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
KIIFB - UWSS to Adoor and adj pt. (2215-01-190-94) 2018-19 - Replacement of 400 mm AC Transmission line and Distribution main by using 400mm DI K9 pipe from TP at Chiranikkal to Parakodu junction in Adoor municipality |
Chiranickal Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
05 Mar 2024 |
work tendered . Only one participant. Bidder quoted 30 % above rate. Tender sanction to be obtained |
Chiranickal WS Section - AE |
|
28 Feb 2024 |
work tendered . Only one participant. Bidder quoted 30 % above rate. Tender sanction to be obtained |
Chiranickal WS Section - AE |
|
23 Feb 2024 |
work tendered . Only one participant. Bidder quoted 30 % above rate. Tender sanction to be obtained |
Chiranickal WS Section - AE |
|
19 Feb 2024 |
work tendered . Only one participant. Bidder quoted 30 % above rate. Tender sanction to be obtained |
Chiranickal WS Section - AE |
|
13 Feb 2024 |
work tendered . Only one participant. Bidder quoted 30 % above rate. Tender sanction to be obtained |
Chiranickal WS Section - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
01/05/2023 |
Scheduled date of Completion of the Project |
31 Dec 2023 |
Expected date of Completion |
31/12/2023 |
Processing Dates
AS Date |
30 Dec 2022 |
TS Date |
09 Mar 2023 |