Project | JalJeevanMission- Laying Distribution Lines and providing FHTC's in Vaniyamkulam Panchayath |
---|---|
Project Code | PKDJJM12207649P1 |
Type | Package |
Main Project | JalJeevanMission- Laying Distribution Lines and providing FHTC's in Vaniyamkulam Panchayath |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Supplying Laying Distribution system from Vellarampara GLSR , Minor renovation works to Existing GLSR, providing FHTCs-7541nos |
Status | On-going |
District | Palakkad |
Executing Office | Palakkad Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 296800000 |
TS Number | TS/2020-2021/2020/27806 |
Technical specification | D I , PVC Pipe Laying and Providing FHTCs- 7541 nos, Minor renovation works to Existing GLSR |
Contractor | C T Thambi (Mob: 9495321861) |
Review Date | Review Message | Review Attended By |
---|---|---|
05 Nov 2021 | Speed up work | AEE,AE |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 17/02/2021 |
---|---|
Scheduled date of Completion as per agreement | 16 Aug 2021 |
Expected date of Completion | 31/03/2025 |
TS Date | 29 Dec 2020 |
---|---|
Estimate Approval | 29 Dec 2020 |
NIT Approval | 05 Jan 2021 |
Tender Closing | 22 Jun 2021 |
Technichal Pre-Qualification | 22 Jan 2021 |
Price bid opening | 27 Jan 2021 |
Workorder Date | 17 Feb 2021 |
---|---|
NA | 13 Apr 2021 |
Palakkad Proj Dn AE 4 |
Date: 27/06/2024 |
Work in progress | 92% Completed
148.366/ 153.00 km completed. FHTC -1157 & HTC -2414 , 3700/7541 house connections completed, 3571 nos geo-tagged. Completed minor renovation works to existing Vellarampara GLSR..
Palakkad Proj Dn AE 4 |
Date: 25/06/2024 |
Work in progress | 92% Completed