JalJeevanMission- Laying Distribution Lines and providing FHTC's in Vaniyamkulam Panchayath

Project JalJeevanMission- Laying Distribution Lines and providing FHTC's in Vaniyamkulam Panchayath
Project Code PKDJJM12207649P1
Type Package
Main Project JalJeevanMission- Laying Distribution Lines and providing FHTC's in Vaniyamkulam Panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Supplying Laying Distribution system from Vellarampara GLSR , Minor renovation works to Existing GLSR, providing FHTCs-7541nos
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 296800000
TS Number TS/2020-2021/2020/27806
Technical specification D I , PVC Pipe Laying and Providing FHTCs- 7541 nos, Minor renovation works to Existing GLSR
Contractor C T Thambi (Mob: 9495321861)

Project Review

See All Review messages
Review Date Review Message Review Attended By
05 Nov 2021 Speed up work AEE,AE

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 17/02/2021
Scheduled date of Completion as per agreement 16 Aug 2021
Expected date of Completion 31/03/2025

Processing Dates

TS Date 29 Dec 2020
Estimate Approval 29 Dec 2020
NIT Approval 05 Jan 2021
Tender Closing 22 Jun 2021
Technichal Pre-Qualification 22 Jan 2021
Price bid opening 27 Jan 2021

Approval Dates

Workorder Date 17 Feb 2021
NA 13 Apr 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Palakkad Proj Dn AE 4
Date: 27/06/2024

Work in progress | 92% Completed

148.366/ 153.00 km completed. FHTC -1157 & HTC -2414 , 3700/7541 house connections completed, 3571 nos geo-tagged. Completed minor renovation works to existing Vellarampara GLSR..

Palakkad Proj Dn AE 4
Date: 25/06/2024

Work in progress | 92% Completed

148.366/ 153.00 km completed. FHTC -1157 & HTC -2414 , 3700/7541 house connections completed, 3571 nos geo-tagged. Completed minor renovation works to existing Vellarampara GLSR. .