JalJeevanMission- Laying Distribution Lines and providing FHTC's in Vaniyamkulam Panchayath
Project |
JalJeevanMission- Laying Distribution Lines and providing FHTC's in Vaniyamkulam Panchayath |
Project Code |
PKDJJM12207649 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
UWSS to Vaniyamkulam Panchayath, Supplying Laying Distribution system from Vellarampara GLSR , Minor renovation works to Existing GLSR, providing FHTCs-7762nos |
Status |
On-going |
District |
Palakkad |
Executing Office |
Palakkad Project Dn |
AS Amount (Rs) |
308800000
|
AS Number |
GO(Rt) No. 777/2020/WRD |
TS Amount (Rs) |
296800000 |
TS Number |
TS/2020-2021/2020/27806 |
Total Bill Submitted (Rs) |
193365919 |
Total Bill Paid (Rs) |
193365919 |
Population Benefitted |
35000 |
Capacity in MLD |
10.00 |
Actual Project Completion Date |
31 Dec 2024 |
Coverage |
7541 FHTCs |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JalJeevanMission- Laying Distribution Lines and providing FHTC's in Vaniyamkulam Panchayath |
Project Division Palakkad |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
25 Jun 2024 |
148.366/ 153.00 km completed. FHTC -1157 & HTC -2414 , 3700/7541 house connections completed, 3571 nos geo-tagged. Completed minor renovation works to existing Vellarampara GLSR. |
Palakkad Proj Dn AE 4 |
|
24 Jun 2024 |
148.366/ 153.00 km completed. FHTC -1157 & HTC -2414 , 3700/7541 house connections completed. Completed minor renovation works to existing Vellarampara GLSR. |
Palakkad Proj Dn AE 4 |
|
22 Jun 2024 |
148.366/ 153.00 km completed,. Remaining DI, PVC & GI Pipe laying work progressing. Culvert Gap work in progress. FHTC -1157 & HTC -2414 3700/7541 house connections completed |
Palakkad Proj Dn AE 4 |
|
18 Jun 2024 |
148.366/ 153.00 km completed,. Remaining DI, PVC & GI Pipe laying work progressing. Culvert Gap work in progress. FHTC -1142 & HTC -2558 3700/7541 house connections completed |
Palakkad Proj Dn AE 4 |
|
15 Jun 2024 |
148.366/ 153.00 km completed,. Remaining DI, PVC & GI Pipe laying work progressing. Culvert Gap work in progress. FHTC -1142 & HTC -2558 3700/7541 house connections completed |
Palakkad Proj Dn AE 4 |
|
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
01 Nov 2021 |
Pending |
Pending |
Approval/Permissions Related (from other departments excluding road cut permission and land related) |
Sanction not obtained for laying pipes in Vaniyamkulam vallappuzha road |
No comments available. |
Pending |
Duration & Sanction dates
Date of start of Project |
17/02/2021 |
Scheduled date of Completion of the Project |
16 Aug 2021 |
Expected date of Completion |
31/12/2024 |
Processing Dates
AS Date |
24 Dec 2020 |
TS Date |
29 Dec 2020 |