KIIFB - 2016 - 2017 Augmentation of WSS to Nemmara,Ayilur and Melarcode panchayaths Phase-II-Package II- Balance work of supplying, Laying, Testing, Commissioning and maintenance of Clear water Pumping main,Distribution lines for Ayilur and Melarcode Zones and balance works of 9.50LL OHSR at Kadampidi in Melarcode Panchayath
Project |
KIIFB - 2016 - 2017 Augmentation of WSS to Nemmara,Ayilur and Melarcode panchayaths Phase-II-Package II- Balance work of supplying, Laying, Testing, Commissioning and maintenance of Clear water Pumping main,Distribution lines for Ayilur and Melarcode Zones and balance works of 9.50LL OHSR at Kadampidi in Melarcode Panchayath |
Project Code |
PKDKIIFB1117627P1 |
Type |
Package |
Main Project |
KIIFB - 16-17 - Augmentation of Nenmara, Ayiloor and Melarcode in Chittur and Alathur Taluk in Palakkad District- Phase II-
|
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
KIIFB - 2016 - 2017 Augmentation of WSS to Nemmara,Ayilur and Melarcode panchayaths Phase-II-Package II- Balance work of supplying, Laying, Testing, Commissioning and maintenance of Clear water Pumping main,Distribution lines for Ayilur and Melarcode Zones and balance works of 9.50LL OHSR at Kadampidi in Melarcode Panchayath |
Status |
On-going |
District |
Palakkad |
Executing Office |
Chittur Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
81800000 |
TS Number |
TS/2019-2020/2019/11568 dated 20-03-2020 |
Technical specification |
Balance work of supplying, Laying, Testing, Commissioning and maintenance of Clear water Pumping main,Distribution lines for Ayilur and Melarcode Zones and balance works of 9.50LL OHSR at Kadampidi in Melarcode Panchayath |
Contractor |
C.M Abdul khader (Mob: 9447010744) |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
10/08/2020 |
Scheduled date of Completion as per agreement |
09 May 2021 |
Expected date of Completion |
28/02/2023 |
Processing Dates
TS Date |
20 Mar 2020 |
Estimate Approval |
20 Mar 2020 |
NIT Approval |
02 May 2020 |
Tender Closing |
02 May 2020 |
Technichal Pre-Qualification |
16 Jul 2020 |
Price bid opening |
05 May 2020 |
Approval Dates
NA |
07 Aug 2019 |
Workorder Date |
10 Aug 2020 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Chittur Project Dn - AE 3 |
Date: 31/03/2023 |
Work has been completed | 100% Completed
work completed on 28.01.2023.
Chittur Project Dn - AE 3 |
Date: 24/03/2023 |
Work in progress | 98% Completed
pack-2-KIIFb-leak rectification work in progress,painting work completed,linking works are also IN PROGRSS.