KIIFB - 2016 - 2017 Augmentation of WSS to Nemmara,Ayilur and Melarcode panchayaths Phase-II-Package II- Balance work of supplying, Laying, Testing, Commissioning and maintenance of Clear water Pumping main,Distribution lines for Ayilur and Melarcode Zones and balance works of 9.50LL OHSR at Kadampidi in Melarcode Panchayath

Project KIIFB - 2016 - 2017 Augmentation of WSS to Nemmara,Ayilur and Melarcode panchayaths Phase-II-Package II- Balance work of supplying, Laying, Testing, Commissioning and maintenance of Clear water Pumping main,Distribution lines for Ayilur and Melarcode Zones and balance works of 9.50LL OHSR at Kadampidi in Melarcode Panchayath
Project Code PKDKIIFB1117627P1
Type Package
Main Project KIIFB - 16-17 - Augmentation of Nenmara, Ayiloor and Melarcode in Chittur and Alathur Taluk in Palakkad District- Phase II-
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description KIIFB - 2016 - 2017 Augmentation of WSS to Nemmara,Ayilur and Melarcode panchayaths Phase-II-Package II- Balance work of supplying, Laying, Testing, Commissioning and maintenance of Clear water Pumping main,Distribution lines for Ayilur and Melarcode Zones and balance works of 9.50LL OHSR at Kadampidi in Melarcode Panchayath
Status On-going
District Palakkad
Executing Office Chittur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 81800000
TS Number TS/2019-2020/2019/11568 dated 20-03-2020
Technical specification Balance work of supplying, Laying, Testing, Commissioning and maintenance of Clear water Pumping main,Distribution lines for Ayilur and Melarcode Zones and balance works of 9.50LL OHSR at Kadampidi in Melarcode Panchayath
Contractor C.M Abdul khader (Mob: 9447010744)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 10/08/2020
Scheduled date of Completion as per agreement 09 May 2021
Expected date of Completion 28/02/2023

Processing Dates

TS Date 20 Mar 2020
Estimate Approval 20 Mar 2020
NIT Approval 02 May 2020
Tender Closing 02 May 2020
Technichal Pre-Qualification 16 Jul 2020
Price bid opening 05 May 2020

Approval Dates

NA 07 Aug 2019
Workorder Date 10 Aug 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chittur Project Dn - AE 3
Date: 31/03/2023

Work has been completed | 100% Completed

work completed on 28.01.2023.

Chittur Project Dn - AE 3
Date: 24/03/2023

Work in progress | 98% Completed

pack-2-KIIFb-leak rectification work in progress,painting work completed,linking works are also IN PROGRSS.