Project | PACKAGE III-Construction of new weir at Mannayam, about three KMs upstream side of the Aduthala bridge. |
---|---|
Project Code | KLMGOK0117468P3 |
Type | Package |
Main Project | PROJECTS UNDER KERALA INFRA.INVT. FUND BOARD KIIFB(74)--WSS to Kalluvathukkal Parippallay and Velinalloor(Part) Villages-Phase I (7520) |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | PACKAGE III-Construction of new weir at Mannayam, about three KMs upstream side of the Aduthala bridge. |
Status | On-going |
District | Kollam |
Executing Office | Kollam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 14100000 |
TS Number | 9161/2019 |
Technical specification | Construction of new weir at Mannayam, about three KMs upstream side of the Aduthala bridge. |
Contractor | M/s Minartech Developers (Mob: 9447764721) |
Review Date | Review Message | Review Attended By |
---|---|---|
16 Dec 2021 | DIRECT THE CONTRACTOR TO RESUME THE WORK IMMIDIATLY AS NOW THE WATER LEVEL LOWERED | AEE,AE,EE |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 05/11/2020 |
---|---|
Scheduled date of Completion as per agreement | 31 May 2022 |
Expected date of Completion | 30/04/2024 |
TS Date | 24 Mar 2017 |
---|---|
Estimate Approval | 21 Jan 2021 |
NIT Approval | 11 Jul 2017 |
Tender Closing | 03 Feb 2020 |
Technichal Pre-Qualification | 10 Mar 2020 |
Price bid opening | 10 Mar 2020 |
Workorder Date | 27 Apr 2020 |
---|---|
NA | 05 Nov 2020 |
Kollam Project HD |
Date: 02/05/2024 |
Work in progress | 32% Completed
CC 1st and part bill details uploaded in PFMS portal..
Kollam Project HD |
Date: 01/05/2024 |
Work in progress | 32% Completed
CC 1st and part bill details uploaded in PFMS portal..