Project | Budget -2017-2018-KIIFB project-TRAN10:WRD 025-13-WSS to Ramanchadi- Aligarh in Malappuram District- Package 5 |
---|---|
Project Code | MLPKIIFB1118510P8 |
Type | Package |
Main Project | Budget -2017-2018-KIIFB project-TRAN10:WRD 025-13-WSS to Ramanchadi- Aligarh in Malappuram District |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | Interconnecting CWGM from MES Road Jn to 3.5LL GLSR near Cricket Stadium Thekkinkode and Laying distributionlines to Angadippuram GP, 3.5LL GLSR near Cricket Stadium Thekkinkode, Laying of 350mm DI K9 CWGM from 3.5 LL Capacity OHSR(Cricket Stadium) for Connectiing CWGM towads Cherakkaparamba Tank at Vylongara Jn, Construction of 10LL OHSR at KWA Office Compound Kunnapalli, Construction of 2.0 LL capacity Wash water sump and Interconnection of new OHSR at AMU campus with old tank |
Status | On-going |
District | Malappuram |
Executing Office | Malappuram Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 115700000 |
TS Number | TS/2022-2023/2022/17585 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | 31/05/2024 |
TS Date | 07 Jul 2022 |
---|---|
Estimate Approval | 07 Jul 2022 |
Malappuram Project Dn AE3 |
Date: 03/05/2024 |
Work has started | 0% Completed
Got TS approval. Waiting for KIIFB project execution document approval to start tendering process. .
Malappuram Project Dn AE3 |
Date: 02/05/2024 |
Work has started | 0% Completed
Got TS approval. Waiting for KIIFB project execution document approval to start tendering process. .