Jal Jeevan Mission JJM-Jal Jeevan Mission 2021-24 Phase II- WSS to Velur Panchayath-Providing Distribution Network and FHTC to Velur Panchayath

Project Jal Jeevan Mission JJM-Jal Jeevan Mission 2021-24 Phase II- WSS to Velur Panchayath-Providing Distribution Network and FHTC to Velur Panchayath
Project Code TCRJJM052213965
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission JJM-Jal Jeevan Mission 2021-24 Phase II- WSS to Velur Panchayath-Providing Distribution Network and FHTC to Velur Panchayath
Status On-going
District Thrissur
Executing Office Nattika Project Dn
AS Amount (Rs) 646993000
AS Number G.O.(Rt) No.401/2022/WRD
TS Amount (Rs) 396000000
TS Number WRD/KWA-CEP/EST-TS/126/2022-5_1_1
Total Bill Submitted (Rs) 4522067
Total Bill Paid (Rs) 4522067
Population Benefitted 6324
Capacity in MLD 52.00
Actual Project Completion Date Date is not specified
Coverage Velur Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-Jal Jeevan Mission 2021-24 Phase II-WSS to Velur Panchayath-Construction of 10.50 LL OHSR-General Civil Work Nattika Project Dn
2 Jal Jeevan Mission JJM-Jal Jeevan Mission 2021-24 Phase II- WSS to Velur Panchayath-Providing Distribution Network and FHTC to Velur Panchayath Nattika Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
25 Jun 2024 84096/140166m pipe laid(250mm DI pipe-464m, 200mm DI pipe-1909.5m, 160 mm HDPE-1157m, 110 mm HDPE-9312m, 90 mm HDPE-41692, 90mm PVC-2364.5m, 75 mm PVC-9495m, 63 mm PVC-14584m, 50mm PVC-2376m, 40mm PVC-1284m). Geo Tagging - 2236/5824 Nos. FHTC- 2270/5824 Nos., Road restoration-37866/114700m. Road restoration-lsgd chipping carpet-9821/16466m. Nattika Project Dn
24 Jun 2024 84096/140166m pipe laid(250mm DI pipe-464m, 200mm DI pipe-1909.5m, 160 mm HDPE-1157m, 110 mm HDPE-9312m, 90 mm HDPE-41692, 90mm PVC-2364.5m, 75 mm PVC-9495m, 63 mm PVC-14584m, 50mm PVC-2376m, 40mm PVC-1284m). Geo Tagging - 2235/5824 Nos. FHTC- 2270/5824 Nos., Road restoration-37866/114700m. Road restoration-lsgd chipping carpet-9821/16466m. Nattika Project Dn
23 Jun 2024 84096/140166m pipe laid(250mm DI pipe-464m, 200mm DI pipe-1909.5m, 160 mm HDPE-1157m, 110 mm HDPE-9312m, 90 mm HDPE-41692, 90mm PVC-2364.5m, 75 mm PVC-9495m, 63 mm PVC-14584m, 50mm PVC-2376m, 40mm PVC-1284m). Geo Tagging - 2231/5824 Nos. FHTC- 2270/5824 Nos., Road restoration-37866/114700m. Road restoration-lsgd chipping carpet-9821/16466m. Nattika Project Dn
22 Jun 2024 84096/140166m pipe laid(250mm DI pipe-464m, 200mm DI pipe-1909.5m, 160 mm HDPE-1157m, 110 mm HDPE-9312m, 90 mm HDPE-41692, 90mm PVC-2364.5m, 75 mm PVC-9495m, 63 mm PVC-14584m, 50mm PVC-2376m, 40mm PVC-1284m). Geo Tagging - 2231/5824 Nos. FHTC- 2270/5824 Nos., Road restoration-37866/114700m. Road restoration-lsgd chipping carpet-9821/16466m. Nattika Project Dn
21 Jun 2024 84096/140166m pipe laid(250mm DI pipe-464m, 200mm DI pipe-1909.5m, 160 mm HDPE-1157m, 110 mm HDPE-9312m, 90 mm HDPE-41692, 90mm PVC-2364.5m, 75 mm PVC-9495m, 63 mm PVC-14584m, 50mm PVC-2376m, 40mm PVC-1284m). Geo Tagging - 2228/5824 Nos. FHTC- 2264/5824 Nos., Road restoration-37866/114700m. Road restoration-lsgd chipping carpet-9821/16466m. Nattika Project Dn

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 18/03/2023
Scheduled date of Completion of the Project 18 Mar 2024
Expected date of Completion 18/03/2024

Processing Dates

AS Date 13 May 2022
TS Date 27 Oct 2022

Other details

Project Officers View