Jal Jeevan Mission JJM-Jal Jeevan Mission 2021-24 Phase II- WSS to Velur Panchayath-Providing Distribution Network and FHTC to Velur Panchayath

Project Jal Jeevan Mission JJM-Jal Jeevan Mission 2021-24 Phase II- WSS to Velur Panchayath-Providing Distribution Network and FHTC to Velur Panchayath
Project Code TCRJJM052213965P1
Type Package
Main Project Jal Jeevan Mission JJM-Jal Jeevan Mission 2021-24 Phase II- WSS to Velur Panchayath-Providing Distribution Network and FHTC to Velur Panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission JJM-Jal Jeevan Mission 2021-24 Phase II- WSS to Velur Panchayath-Providing Distribution Network and FHTC to Velur Panchayath
Status On-going
District Thrissur
Executing Office Nattika Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 396000000
TS Number WRD/KWA-CEP/EST-TS/126/2022-5_1_1
Technical specification Providing Distribution Network and FHTC to Velur Panchayath

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 18/03/2023
Scheduled date of Completion as per agreement 17 Mar 2024
Expected date of Completion 18/03/2024

Processing Dates

TS Date 27 Oct 2022
Estimate Approval 27 Oct 2022
NIT Approval 29 Oct 2022
Tender Closing 31 Oct 2022
Technichal Pre-Qualification 14 Feb 2023
Price bid opening 13 Mar 2023

Approval Dates

Workorder Date 18 Mar 2023
NA 26 May 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Nattika Project Dn
Date: 27/06/2024

Work in progress | 32% Completed

84096/140166m pipe laid(250mm DI pipe-464m, 200mm DI pipe-1909.5m, 160 mm HDPE-1157m, 110 mm HDPE-9312m, 90 mm HDPE-41692, 90mm PVC-2364.5m, 75 mm PVC-9495m, 63 mm PVC-14584m, 50mm PVC-2376m, 40mm PVC-1284m). Geo Tagging - 2238/5824 Nos. FHTC- 2270/5824 Nos., Road restoration-37866/114700m. Road restoration-lsgd chipping carpet-9821/16466m..

Nattika Project Dn
Date: 26/06/2024

Work in progress | 32% Completed

84096/140166m pipe laid(250mm DI pipe-464m, 200mm DI pipe-1909.5m, 160 mm HDPE-1157m, 110 mm HDPE-9312m, 90 mm HDPE-41692, 90mm PVC-2364.5m, 75 mm PVC-9495m, 63 mm PVC-14584m, 50mm PVC-2376m, 40mm PVC-1284m). Geo Tagging - 2236/5824 Nos. FHTC- 2270/5824 Nos., Road restoration-37866/114700m. Road restoration-lsgd chipping carpet-9821/16466m..