KIIFB-2016-17-WRD 002-09- Augmentation of WSS to Kottayam Municipality, Package IV- Restoration of road damaged by laying pipelines along NH 183 (KK Road) on both sides in Kottayam Municipal area under NH Roads Division, Muvattupuzha

Project KIIFB-2016-17-WRD 002-09- Augmentation of WSS to Kottayam Municipality, Package IV- Restoration of road damaged by laying pipelines along NH 183 (KK Road) on both sides in Kottayam Municipal area under NH Roads Division, Muvattupuzha
Project Code KTMKIIFB0117545P5
Type Package
Main Project KIIFB-2016-17- WRD-002-09 Augmentation of UWSS to Kottayam Municipality
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description This work involves the road restoration part for the pipe laying works long KK Road (NH 183) from Collectorate to Kanjikuzhi junction on both sides.
Status On-going
District Kottayam
Executing Office Kottayam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 5433200
TS Number TS/2021-2022/2021/14225
Technical specification Restoring the NH 183 road to BM/BC standards after pipe laying as per MoRD /MoRTH specifications

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 24/09/2021
Scheduled date of Completion as per agreement 03 Mar 2022
Expected date of Completion 16/12/2022

Processing Dates

TS Date 25 Jun 2021
Estimate Approval 19 Jul 2021
NIT Approval 19 Jul 2021
Tender Closing 30 Jul 2021
Technichal Pre-Qualification 02 Aug 2021
Price bid opening 05 Aug 2021

Approval Dates

Workorder Date 13 Oct 2021
NA 24 Sep 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kottayam Proj Dn AE4
Date: 12/03/2024

Work has started | 0% Completed

This work involves road restoration on NH 183.Due to the non-availability of permission for laying pipes, restoration cannot be started. Hence decided to foreclose the work .

Kottayam Proj Dn AE4
Date: 11/03/2024

Work has started | 0% Completed

This work involves road restoration on NH 183.Due to the non-availability of permission for laying pipes, restoration cannot be started. Hence decided to foreclose the work .