Jal Jeevan Mission (JJM) - JJM PHASE 2- 2021-24 WSS to Desamangalam, Varavoor, Erumapetty, Kadangode, Velur ,Mulloorkara part,Choondal,Kandanassery and Elavally Panchayaths in Thrissur District – Package - I - Construction of 40 MLD WTP at DESAMANGALAM.
Project |
Jal Jeevan Mission (JJM) - JJM PHASE 2- 2021-24 WSS to Desamangalam, Varavoor, Erumapetty, Kadangode, Velur ,Mulloorkara part,Choondal,Kandanassery and Elavally Panchayaths in Thrissur District – Package - I - Construction of 40 MLD WTP at DESAMANGALAM. |
Project Code |
TCRJJM052215569 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM PHASE 2- 2021-22 WSS to Desamangalam, Varavoor, Erumapetty, Kadangode, Velur ,Choondal,Kandanassery Panchayath-Construction of 40mld Water Treatment Plant |
Status |
On-going |
District |
Thrissur |
Executing Office |
Nattika Project Dn |
AS Amount (Rs) |
4497130000
|
AS Number |
G.O.(Rt) No.401/2022/WRD |
TS Amount (Rs) |
330800000 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/14790/2023_5_1_1 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
32483 |
Capacity in MLD |
40.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Desamangalam, Varavoor, Erumapetty, Kadangode, Velur ,Choondal,Kandanassery Panchayath-Construction of 40mld Water Treatment Plant- |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM) - JJM PHASE 2- 2021-24 WSS to Desamangalam, Varavoor, Erumapetty, Kadangode, Velur ,Mulloorkara part,Choondal,Kandanassery and Elavally Panchayaths in Thrissur District – Package - I - Construction of 40 MLD WTP at DESAMANGALAM. |
Nattika Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
06 Mar 2024 |
work not started |
Nattika Project Dn |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
30/10/2023 |
Scheduled date of Completion of the Project |
30 Apr 2025 |
Expected date of Completion |
29/04/2025 |
Processing Dates
AS Date |
13 May 2022 |
TS Date |
07 Aug 2023 |