KIIFB 2016-17-WRD 002-07- WSS to koyilandy muncipality and adjoining panchayath (phase1)-Package4

Project KIIFB 2016-17-WRD 002-07- WSS to koyilandy muncipality and adjoining panchayath (phase1)-Package4
Project Code CLTKIIFB1117507P4
Type Package
Main Project KIIFB-2016-17-WRD 002-07- WSS to koyilandy muncipality and adjoining panchayath (phase1)
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Construction of 27 LL OHSR at kottoor for kottoor and Naduvannoor G.P and laying clear water gravity main (350mm DI-200m, 250mm DI-150m, 400mm DI -350m) to OHSR at valloramala from Kottoor Junction
Status On-going
District Kozhikkode
Executing Office Kozhikode Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 45000000
TS Number TS/2019-2020/2019/14951
Technical specification Design, Construction and commissioning of 27 LL capacity OHSR, Construction of Retaining/ Compound wall and Watchman's room at valloramala ,supplying, Laying,Tesing and commissioning of clear water transmission main.
Contractor O Abdul Majeed (Mob: 9447184489)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 07/03/2020
Scheduled date of Completion as per agreement 19 Feb 2021
Expected date of Completion 31/03/2023

Processing Dates

TS Date 06 Dec 2019
Estimate Approval 06 Dec 2019
NIT Approval 17 Dec 2019
Tender Closing 04 Feb 2020
Price bid opening 07 Feb 2020

Approval Dates

Workorder Date 20 Feb 2020
NA 07 Mar 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kozhikode Project Dn AE5
Date: 31/03/2023

Work has been completed | 100% Completed

Work completed..

Kozhikode Project Dn AE5
Date: 30/03/2023

Work in progress | 99% Completed

1)All columns completed, 2)Floor slab RCC work completed, 3)Compound wall 95% work completed, 4)Stair case work completed, 5)Watchman room work completed, 6)side wall completed, 7) Roof slab and beam RCC work completed, 8) Plastering working completed, 9) Floor slab level hand rail work completed, 10)Pipe supplied, 11) 350mm and 400mm DI laying work completed, 12) Finishing work in progress. .