Project | KIIFB 2016-17-WRD 002-07- WSS to koyilandy muncipality and adjoining panchayath (phase1)-Package4 |
---|---|
Project Code | CLTKIIFB1117507P4 |
Type | Package |
Main Project | KIIFB-2016-17-WRD 002-07- WSS to koyilandy muncipality and adjoining panchayath (phase1) |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | Construction of 27 LL OHSR at kottoor for kottoor and Naduvannoor G.P and laying clear water gravity main (350mm DI-200m, 250mm DI-150m, 400mm DI -350m) to OHSR at valloramala from Kottoor Junction |
Status | On-going |
District | Kozhikkode |
Executing Office | Kozhikode Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 45000000 |
TS Number | TS/2019-2020/2019/14951 |
Technical specification | Design, Construction and commissioning of 27 LL capacity OHSR, Construction of Retaining/ Compound wall and Watchman's room at valloramala ,supplying, Laying,Tesing and commissioning of clear water transmission main. |
Contractor | O Abdul Majeed (Mob: 9447184489) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 07/03/2020 |
---|---|
Scheduled date of Completion as per agreement | 19 Feb 2021 |
Expected date of Completion | 31/03/2023 |
TS Date | 06 Dec 2019 |
---|---|
Estimate Approval | 06 Dec 2019 |
NIT Approval | 17 Dec 2019 |
Tender Closing | 04 Feb 2020 |
Price bid opening | 07 Feb 2020 |
Workorder Date | 20 Feb 2020 |
---|---|
NA | 07 Mar 2020 |
Kozhikode Project Dn AE5 |
Date: 31/03/2023 |
Work has been completed | 100% Completed
Work completed..
Kozhikode Project Dn AE5 |
Date: 30/03/2023 |
Work in progress | 99% Completed
1)All columns completed, 2)Floor slab RCC work completed, 3)Compound wall 95% work completed, 4)Stair case work completed, 5)Watchman room work completed, 6)side wall completed, 7) Roof slab and beam RCC work completed, 8) Plastering working completed, 9) Floor slab level hand rail work completed, 10)Pipe supplied, 11) 350mm and 400mm DI laying work completed, 12) Finishing work in progress. .