Project | Jal Jeevan Mission (JJM) - Pampakkuda Panchayath - Providing remaining FHTC to rural Households of Phase 1- Part II-Pipeline Work |
---|---|
Project Code | EKMJJM082014733P1 |
Type | Package |
Main Project | Jal Jeevan Mission (JJM) - Pampakkuda Panchayath - Providing remaining FHTC to rural Households of Phase 1- Part II-Pipeline Work |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission (JJM) - Pampakkuda Panchayath - Providing remaining FHTC to rural Households of Phase 1- Part II-Pipeline Work |
Status | On-going |
District | Ernakulam |
Executing Office | Piravam PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 5110785 |
TS Number | TS/11288/2022_26_5_4 dated 14/07/2023 Reg No.8678/2023-2024 |
Technical specification | Nil |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 09/08/2023 |
---|---|
Scheduled date of Completion as per agreement | 08 Feb 2024 |
Expected date of Completion | 08/02/2024 |
TS Date | 14 Jul 2023 |
---|---|
Estimate Approval | 14 Jul 2023 |
NIT Approval | 14 Jul 2023 |
Tender Closing | 26 Jul 2023 |
Technichal Pre-Qualification | 29 Jul 2023 |
Price bid opening | 29 Jul 2023 |
Workorder Date | 04 Aug 2023 |
---|---|
NA | 09 Aug 2023 |
Piravom Sn - AE |
Date: 25/06/2024 |
Work in progress | 35% Completed
Work in progress.
Piravom Sn - AE |
Date: 13/06/2024 |
Work in progress | 35% Completed
Work in progress.