- Home
- Jal Jeevan Mission (JJM) - Pampakkuda Pa...
Jal Jeevan Mission (JJM) - Pampakkuda Panchayath - Providing remaining FHTC to rural Households of Phase 1- Part II-Pipeline Work
Project |
Jal Jeevan Mission (JJM) - Pampakkuda Panchayath - Providing remaining FHTC to rural Households of Phase 1- Part II-Pipeline Work |
Project Code |
EKMJJM082014733 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission (JJM) - Pampakkuda Panchayath - Providing remaining FHTC to rural Households of Phase 1- Part II-Pipeline Work |
Status |
On-going |
District |
Ernakulam |
Executing Office |
Muvattupuzha PH Dn |
AS Amount (Rs) |
17700000
|
AS Number |
G.O.(Rt)No.541/2020/WRD dated 21/08/2020 |
TS Amount (Rs) |
5110785 |
TS Number |
TS/11288/2022_26_5_4 dated 14/07/2023 Reg No.8678/2023-2024 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
5000 |
Capacity in MLD |
0.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Pampakkuda Panchayath - Providing remaining FHTC to rural Households of Phase 1 |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM) - Pampakkuda Panchayath - Providing remaining FHTC to rural Households of Phase 1- Part II-Pipeline Work |
Piravam PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
25 Jun 2024 |
Work in progress |
Piravom Sn - AE |
|
13 Jun 2024 |
Work in progress |
Piravom Sn - AE |
|
29 May 2024 |
Work in progress |
Piravom Sn - AE |
|
23 May 2024 |
Work in progress |
Piravom Sn - AE |
|
10 May 2024 |
Work in progress |
Piravom Sn - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
09/08/2023 |
Scheduled date of Completion of the Project |
08 Feb 2024 |
Expected date of Completion |
08/02/2024 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
14 Jul 2023 |