DEPOSIT-KRFB-Hill Highway KRFB-2017-2018- Improvements to Peerumedu , Devikulam road KM 19/000 to 40/050 and Thodupuzha -Puliyanmala road KM 85/500 to 92/167 in Idukki dist. - shifting of KWA utilities
| Project |
DEPOSIT-KRFB-Hill Highway KRFB-2017-2018- Improvements to Peerumedu , Devikulam road KM 19/000 to 40/050 and Thodupuzha -Puliyanmala road KM 85/500 to 92/167 in Idukki dist. - shifting of KWA utilities |
| Project Code |
IDKGOK112215574 |
| Type |
Main project |
| Funding Agency |
GOK |
| Category |
Deposit Work |
| Type of scheme |
Water Supply |
| Scheme |
4215-01-800-89 |
| Description |
DEPOSIT-KRFB-Hill Highway KRFB-2017-2018- Improvements to Peerumedu, Devikulam road KM 19/000 to 40/050 and Thodupuzha -Puliyanmala road KM 85/500 to 92/167 in Idukki dist. - shifting of KWA utilities |
| Status |
On-going |
| District |
Idukki |
| Executing Office |
Kattappana Project Dn |
| AS Amount (Rs) |
54093930
|
| AS Number |
KRFB/PMU/MVPA-IDK/HH-PD/2021 |
| TS Amount (Rs) |
16810000 |
| TS Number |
WRD/KWA-CE(CR)/EST_TS/12798/2022_26_3_2 |
| Total Bill Submitted (Rs) |
8268312 |
| Total Bill Paid (Rs) |
8268312 |
| Population Benefitted |
56780 |
| Capacity in MLD |
7.00 |
| Actual Project Completion Date |
08 Jun 2024 |
| Coverage |
Chappath to Idukkikavala |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
Improvement works to peerumedu devikulam road from Chappath to Marykulam: Shifting of utilities |
Project Division Kattapana |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 08 Jul 2025 |
Laid 562.5 metres of 350mm DI, 1481 metres of 200mm PVC pipe, 3702 metres of 80mm GI pipe, 32 metres of 350 mm MS and 42 metres of 200mm MS. So far, laid 5819.5 metres of pipeline out of 5904 metres. |
Kattappana AEE 1 |
|
| 05 Jul 2025 |
Laid 562.5 metres of 350mm DI, 1481 metres of 200mm PVC pipe, 3702 metres of 80mm GI pipe, 32 metres of 350 mm MS and 42 metres of 200mm MS. So far, laid 5819.5 metres of pipeline out of 5904 metres. |
Kattapana AE 1 |
|
| 02 Jul 2025 |
Laid 562.5 metres of 350mm DI, 1481 metres of 200mm PVC pipe, 3702 metres of 80mm GI pipe, 32 metres of 350 mm MS and 42 metres of 200mm MS. So far, laid 5819.5 metres of pipeline out of 5904 metres. |
Kattapana AE 1 |
|
| 29 Jun 2025 |
Laid 562.5 metres of 350mm DI, 1481 metres of 200mm PVC pipe, 3702 metres of 80mm GI pipe, 32 metres of 350 mm MS and 42 metres of 200mm MS. So far, laid 5819.5 metres of pipeline out of 5904 metres. |
Kattappana AEE 1 |
|
| 26 Jun 2025 |
Laid 562.5 metres of 350mm DI, 1481 metres of 200mm PVC pipe, 3702 metres of 80mm GI pipe, 32 metres of 350 mm MS and 42 metres of 200mm MS. So far, laid 5819.5 metres of pipeline out of 5904 metres. |
Kattappana AEE 1 |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
13/02/2024 |
| Scheduled date of Completion of the Project |
29 Dec 2024 |
| Expected date of Completion |
31/10/2024 |
Processing Dates
| AS Date |
01 Nov 2022 |
| TS Date |
03 Nov 2023 |