| Project | Improvement works to peerumedu devikulam road from Chappath to Marykulam: Shifting of utilities |
|---|---|
| Project Code | IDKGOK112215574P1 |
| Type | Package |
| Main Project | DEPOSIT-KRFB-Hill Highway KRFB-2017-2018- Improvements to Peerumedu , Devikulam road KM 19/000 to 40/050 and Thodupuzha -Puliyanmala road KM 85/500 to 92/167 in Idukki dist. - shifting of KWA utilities |
| Funding Agency | GOK |
| Category | Deposit Work |
| Type of scheme | Water Supply |
| Scheme | 4215-01-800-89 |
| Description | Improvement works to peerumedu devikulam road from Chappath to Marykulam: Shifting of utilities |
| Status | On-going |
| District | Idukki |
| Executing Office | Kattappana Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 16810000 |
| TS Number | WRD/KWA-CE(CR)/EST_TS/12798/2022_26_3_2 |
| Technical specification | PVC Pipe, 10kg/cm2, 200mm Dia- 1550m DI K9 Pipe, 350mm Dia- 580m 80mm GI- 3700m |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 13/02/2024 |
|---|---|
| Scheduled date of Completion as per agreement | 29 Dec 2024 |
| Expected date of Completion | 31/12/2024 |
| TS Date | 03 Nov 2023 |
|---|---|
| Estimate Approval | 07 Nov 2023 |
| NIT Approval | 14 Nov 2023 |
| Tender Closing | 13 Nov 2023 |
| Workorder Date | 17 Nov 2023 |
|---|---|
| NA | 28 Nov 2023 |
| Kattappana AEE 1 |
| Date: 14/01/2026 |
Work has been completed | 100% Completed
completed.
| Kattappana AEE 1 |
| Date: 13/01/2026 |
Work in progress | 90% Completed
Laid 562.5 metres of 350mm DI, 1481 metres of 200mm PVC pipe, 3702 metres of 80mm GI pipe, 32 metres of 350 mm MS and 42 metres of 200mm MS. So far, laid 5819.5 metres of pipeline out of 5904 metres..