Project | KIIFB 2017-18- CWSS to Resolve the Scarcity of Drinking Water in various Grama Panchayaths in Malampuzha in Palakkad District Phase-I-package-I |
---|---|
Project Code | PKDKIIFB1118630P5 |
Type | Package |
Main Project | KIIFB 2017-18- CWSS to Resolve the Scarcity of Drinking Water in various Grama Panchayaths in Malampuzha in Palakkad District Phase-I |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | KIIFB 2017-18- CWSS to Resolve the Scarcity of Drinking Water in various Grama Panchayaths in Malampuzha in Palakkad District Phase-I-package-I 8LL OHSR at at Malmpuzha KWA Compound,200mm DI CWPM to 8LL OHSR, 7LL OHSR at Padalikkaad, 350mm DI CW Common Pumping main and 200mm DI Branch Pumping main, 11LL OHSR at JTS Compound, 300mm DI CWPM , Pump house and Motor Pump sets |
Status | On-going |
District | Palakkad |
Executing Office | Chittur Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 156000000 |
TS Number | TS/2019-2020/2019/11960 dated 04-03-2020 |
Technical specification | 8LL OHSR at at Malmpuzha KWA Compound,200mm DI CWPM to 8LL OHSR, 7LL OHSR at Padalikkaad, 350mm DI CW Common Pumping main and 200mm DI Branch Pumping main, 11LL OHSR at JTS Compound, 300mm DI CWPM , Pump house and Motor Pump sets |
Contractor | Prem construction (Mob: 8109898554) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 19/02/2020 |
---|---|
Scheduled date of Completion as per agreement | 18 Feb 2021 |
Expected date of Completion | 30/06/2024 |
TS Date | 05 Oct 2019 |
---|---|
Estimate Approval | 05 Oct 2019 |
NIT Approval | 10 Oct 2019 |
Tender Closing | 14 Nov 2019 |
Technichal Pre-Qualification | 18 Nov 2019 |
Price bid opening | 18 Nov 2019 |
NA | 04 Mar 2020 |
---|---|
Workorder Date | 19 Feb 2020 |
Chittur Project Dn - AE 2 |
Date: 23/04/2024 |
Work in progress | 90% Completed
350mm DI pipe pumping main- anchor block casting work in progress, SCOUR LINE laying work in progress Pumping main including Railway crossing work completed except valve and valve chambers work in progress, Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house completed on 1.05.2023 1) 11 LL OHSR at JTS –plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – colour washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad and store room construction work in progress 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge- work completed except painting work.
Chittur Project Dn - AE 2 |
Date: 11/04/2024 |
Work in progress | 90% Completed
350mm DI pipe pumping main- anchor block casting work in progress, SCOUR LINE laying work in progress Pumping main including Railway crossing work completed except valve and valve chambers work in progress, Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house completed on 1.05.2023 1) 11 LL OHSR at JTS –plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – colour washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad and store room construction work in progress 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge- work completed except painting work.